Construction Closure Overview
Construction Logistics Brook St. – Enabling & Fluid Dynamics
- January 2026 – May 2026
- No Changes to Brook Street Area
Construction Logistics Hope St. – Enabling & Fluid Dynamics
- Fire lane to remain open – daily work at north stair
- Brown dumpsters to be relocated / worked with construction laydown area
- Stair tower to be installed next to building for construction access inside temporary fence enclosure
- Loading dock access to be coordinated with Brown
Construction Updates
Please note, scope may change based on existing conditions found in the field.
MARCH 2026
Week of March 23, 2026
- LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH Enabling L01/02 – Relocate electrical and fire alarm conduits including level 02 on column line D where possible
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Start MEP rough-in
- LIDH Enabling L02 – Demo existing hatch and steel infill
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Install geofoam for pit, infill trenches
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Infill concrete hatch on level 2
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Framing & install door frames
- LIDH 102B – Sheetrock IDF room
Week of March 30, 2026
- LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH Enabling L01/02 – Relocate electrical and fire alarm conduits including level 02 on column line D where possible
- LIDH Enabling L01 – Relocate fire alarm control panel to new fire alarm room
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Complete framing & install door frames
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue MEP rough-in
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Tie into existing systems
Week of April 6, 2026
- LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH Enabling L01 – Relocate fire alarm control panel to new fire alarm room
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue MEP rough-in
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Tie into existing systems
Construction Milestones
Mobilization – Enabling / Fluid Dynamics - January 26, 2026
Fluid Dynamics Turn-over - June 4, 2026
Mobilization – Phase 1 - June 12, 2026
Phase 1 Re-Open Hope Street Entrance - April 8, 2027
Phase 1 Turnover - May 4, 2027
Phase 2 Turnover - August 19, 2027
Building Full Weathertight - October 14, 2027
Phase 3 Turnover / Substantial Completion - December 1, 2027
Final Completion / Turn-over - December 9, 2027