Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Phase 1

May 2026 –  January 2027
  • Brook Street Area to receive temporary fencing
  • Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC.
  • Brook Street walkway to ERC will close August 1
  • Level 1 entrance to Prince Lab will remain open at this time until further notice
  • Fire lane will be shut down for tie-in work to street

Construction Logistics Hope St. – Enabling & Fluid Dynamics

May 2026 –  December 2027
  • Hope Street parking lot to receive updated Phase 1 temporary fencing
  • Traffic pattern to adjust to one way from Brook Street

**Note – Minden Hall work by another CM will also be occurring**

Construction Updates

Please note, scope may change based on existing conditions found in the field.

AUGUST  2026 

Week of August 24, 2026
  • LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
  • LIDH L01 – Dual temp. piping removal & replacement
  • LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
  • LIDH L02 - IDF room work to demo and re-pipe conduit from L02 to L01
  • LIDH L02 – Select abatement and demolition of Air Handling Units (Fluid Dynamics)
  • LIDH L02 – Select demolition – unoccupied workshop area and Fluid Dynamics
  • LIDH L02 - Demolition of rooms below the south mezzanine
  • LIDH L02 & L03 – MEP make-safe
  • LIDH Exterior South Façade – Ground protection & prep
Week of August 31, 2026
  • LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
  • LIDH L01 – Dual temp. piping removal & replacement
  • LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
  • LIDH L02 - IDF room work to demo and re-pipe conduit from L02 to L01
  • LIDH L02 – Select demolition at unoccupied workshop area and Fluid Dynamics
  • LIDH L02 & L03 – MEP make-safe
  • LIDH Exterior South Façade – Ground protection & prep

SEPTEMBER  2026 

Week of September 1, 2026
  • LIDH L01 – Continue installation of Sprinkler branch piping throughout Level 1
  • LIDH L01 – Dual temp. piping removal & replacement
  • LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
  • LIDH L02 - IDF room work to demo and re-pipe conduit from L02 to L01
  • LIDH L02 – Select demolition at unoccupied workshop area
  • LIDH L02 & L03 – MEP make-safe
  • LIDH Exterior South Façade – Ground protection & prep
 

Construction Milestones

Mobilization – Enabling / Fluid Dynamics                            January 26, 2026
Mobilization – Phase 1                                                           June 12, 2026
Fluid Dynamics Turn-over                                                     August 4, 2026
Phase 1 Re-Open Brooks Street Entrance                              April 8, 2027
Phase 1 Turnover                                                                    May 4, 2027
Phase 2 Turnover                                                                    August 19, 2027
Building Full Weathertight                                                     October 14, 2027
Phase 3 Turnover / Substantial Completion                           December 1, 2027
Final Completion / Turn-over                                                 December 9, 2027