Construction Closure Overview
Construction Logistics Brook St. – Phase 1
May 2026 – January 2027
- Brook Street Area to receive temporary fencing
- Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC
- Level 1 entrance to Prince Lab will remain open at this time until further notice
- Fire lane will be shut down for tie-in work to street
Construction Logistics Hope St. – Enabling & Fluid Dynamics
May 2026 – December 2027
- Hope Street parking lot to receive updated Phase 1 temporary fencing
- Traffic pattern to adjust to one way from Brook Street
**Note – Minden Hall work by another CM will also be occurring**
Construction Updates
Please note, scope may change based on existing conditions found in the field.
November 2026
Week of November 16, 2026
- Level 01 – Continue installation of Sprinkler branch piping throughout Level 1
- Level 01 – Framing for new restrooms, Material Science Lab, and Fluid Dynamics Conference Room
- Level 01 – Sawcut Fluid Dynamics Conference Room floor
- Level 01 – Form and pour new elevator pit
- Level 01 – Southwest stair re-work and demolition
- Level 02 – Framing for new interior partitions
- Level 03 – Clean, place, and cure new concrete slab on deck
- Roof – Misc. rooftop prep work for steel and mechanical equipment
- Exterior – Install curtain wall framing and glazing at south façade
- Exterior – Form and place cooling tower concrete pad at north elevation
- Exterior – Excavate for new concrete footings at west entrance
Week of November 23, 2026
- Level 01 – Continue installation of Sprinkler branch piping throughout Level 1
- Level 01 – Framing for new restrooms, Material Science Lab, and Fluid Dynamics Conference Room
- Level 01 – Southwest stair re-work and demolition
- Level 01 – Elevator Pit Work
- Level 02 – Framing for new interior partitions
- Level 03 – Framing for new interior partitions
- Roof – Misc. rooftop prep work for steel and mechanical equipment
- Exterior – Install curtain wall framing and glazing at south façade
- Exterior – Excavate for new concrete footings at west entrance
Week of November 30, 2026
- Level 01 – Continue installation of Sprinkler branch piping throughout Level 1
- Level 01 – Framing for new restrooms, Material Science Lab, and Fluid Dynamics Conference Room
- Level 01 – Elevator Pit Work
- Level 01 – Southwest stair re-work and demolition
- Level 02 – Framing for new interior partitions
- Level 03 – Framing for new interior partitions
- Roof – Misc. rooftop prep work for steel and mechanical equipment
- Exterior – Install curtain wall framing and glazing at south façade
- Exterior – Form and place cooling tower concrete pad at north elevation
- Exterior – Excavate for new concrete footings at west entrance
Construction Milestones
Mobilization – Enabling / Fluid Dynamics January 26, 2026
Mobilization – Phase 1 June 12, 2026
Fluid Dynamics Turn-over August 4, 2026
Phase 1 Re-Open Brooks Street Entrance May 13, 2027
Phase 1 Turnover July 28, 2027
Building Full Weathertight November 19, 2027
Phase 2 Turnover / Substantial Completion December 22, 2027
Final Completion / Turn-over December 31, 2027