Construction Closure Overview
Construction Logistics Brook St. – Enabling & Fluid Dynamics
- January 2026 – May 2026
- No Changes to Brook Street Area
Construction Logistics Hope St. – Enabling & Fluid Dynamics
- January 2026 – May 2026
- Fire lane to remain open – daily work at north stair
- Brown dumpsters to be relocated / worked with construction laydown area
- Stair tower to be installed next to building for construction access inside temporary fence enclosure
- Loading dock access to be coordinated with Brown
Construction Updates
Please note, scope may change based on existing conditions found in the field.
MAY/JUNE 2026
Week of May 18, 2026
- LIDH - Mechanical, Plumbing & Electrical / Fire Alarm, low voltage reconnaissance throughout Building
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH Enabling L02 – Swing Space electrical prep
- LIDH Enabling L02 – Plumbing venting tie-in & floor box work
- LIDH Enabling – IDF 102B – Low voltage work
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – MEP punch list, equipment start-up & paint touch-up
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue lab casework install
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Install carbon fiber reinforcements for duct penetration
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Core and saw-cut for exhaust duct penetration
Week of May 25, 2026
- LIDH - Mechanical, Plumbing & Electrical / Fire Alarm, low voltage reconnaissance throughout Building
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH Enabling L02 – Swing Space electrical prep
- LIDH Enabling L02 – Plumbing venting tie-in & floor box work
- LIDH Enabling – IDF 102B – Low voltage work
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – MEP punch list, equipment start-up & paint touch-up
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Board, tape, and paint around wall laboratory fixtures
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue lab casework install
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Build fire rated suspended shaft for exhaust duct risers
Week of June 1, 2026
- LIDH - Mechanical, Plumbing & Electrical / Fire Alarm, low voltage reconnaissance throughout building
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH Enabling L02 – Swing Space electrical prep
- LIDH Enabling L02 – Plumbing venting tie-in & floor box work
- LIDH Enabling – IDF 102B – Low voltage work
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – MEP punch list, equipment start-up, & paint touch-up
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue lab casework, equipment, and fixtures install
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Install storefront windows
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Ceiling and flooring finishes and punch list
Construction Milestones
Mobilization – Enabling / Fluid Dynamics - January 26, 2026
Fluid Dynamics Turn-over - June 4, 2026
Mobilization – Phase 1 - June 12, 2026
Phase 1 Re-Open Hope Street Entrance - April 8, 2027
Phase 1 Turnover - May 4, 2027
Phase 2 Turnover - August 19, 2027
Building Full Weathertight - October 14, 2027
Phase 3 Turnover / Substantial Completion - December 1, 2027
Final Completion / Turn-over - December 9, 2027