Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Enabling & Fluid Dynamics

  • January 2026 – May 2026
    • No Changes to Brook Street Area

Construction Logistics Hope  St. – Enabling & Fluid Dynamics

  • January 2026 – May 2026
    • Fire lane to remain open – daily work at North stair
    • Brown dumpsters to be relocated / worked with construction laydown area
    • Stair tower to be installed next to building for construction access inside temporary fence enclosure
    • Loading dock access to be coordinated with Brown

Construction Updates

Please note, scope may change based on existing conditions found in the field.

APRIL 2026 

Week of April 13, 2026

  • LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance throughout building
  • LIDH - **ALL ROOMS LEVEL 1 – Construction team entering rooms for exploratory**
  • LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue MEP rough-in 
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – MEP inspections
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Top of walls with drywall
  • LIDH 102B – Top off drywall, firestop & install ceiling
  • LIDH Exterior – North stair – excavate for footings

Week of April 20, 2026

  • LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance throughout building
  • LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue MEP rough-in & tie-into existing systems
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue topping off walls (drywall)
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Layout ceiling
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – MEP inspections
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Flooring self leveler
  • LIDH Exterior – Install north terrace stairs
  • LIDH 102B – Painting
  • LIDH 102B – Install flooring

Week of April 27, 2026

  • LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance throughout building
  • LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Overhead MEP & lighting installation
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Drywall walls
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Layout ceiling grid
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Paint 1st coat on walls
  • LIDH 132 – Install ceiling grid
     

Construction Milestones

Mobilization – Enabling / Fluid Dynamics - January 26, 2026
Fluid Dynamics Turn-over - June 4, 2026
Mobilization – Phase 1 - June 12, 2026
Phase 1 Re-Open Hope Street Entrance - April 8, 2027
Phase 1 Turnover - May 4, 2027
Phase 2 Turnover - August 19, 2027
Building Full Weathertight - October 14, 2027
Phase 3 Turnover / Substantial Completion - December 1, 2027
Final Completion / Turn-over - December 9, 2027