Construction Closure Overview
Construction Logistics Brook St. – Phase 1
May 2026 – January 2027
- Brook Street Area to receive temporary fencing
- Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC.
- Brook Street walkway to ERC will close August 1
- Level 1 entrance to Prince Lab will remain open at this time until further notice
- Fire lane will be shut down for tie-in work to street
Construction Logistics Hope St. – Enabling & Fluid Dynamics
May 2026 – December 2027
- Hope Street parking lot to receive updated Phase 1 temporary fencing
- Traffic pattern to adjust to one way from Brook Street
**Note – Minden Hall work by another CM will also be occurring**
Construction Updates
Please note, scope may change based on existing conditions found in the field.
AUGUST 2026
Week of August 24, 2026
- LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
- LIDH L01 – Dual temp. piping removal & replacement
- LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
- LIDH L02 - IDF room work to demo and re-pipe conduit from L02 to L01
- LIDH L02 – Select abatement and demolition of Air Handling Units (Fluid Dynamics)
- LIDH L02 – Select demolition – unoccupied workshop area and Fluid Dynamics
- LIDH L02 - Demolition of rooms below the south mezzanine
- LIDH L02 & L03 – MEP make-safe
- LIDH Exterior South Façade – Ground protection & prep
Week of August 31, 2026
- LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
- LIDH L01 – Dual temp. piping removal & replacement
- LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
- LIDH L02 - IDF room work to demo and re-pipe conduit from L02 to L01
- LIDH L02 – Select demolition at unoccupied workshop area and Fluid Dynamics
- LIDH L02 & L03 – MEP make-safe
- LIDH Exterior South Façade – Ground protection & prep
SEPTEMBER 2026
Week of September 1, 2026
- LIDH L01 – Continue installation of Sprinkler branch piping throughout Level 1
- LIDH L01 – Dual temp. piping removal & replacement
- LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
- LIDH L02 - IDF room work to demo and re-pipe conduit from L02 to L01
- LIDH L02 – Select demolition at unoccupied workshop area
- LIDH L02 & L03 – MEP make-safe
- LIDH Exterior South Façade – Ground protection & prep
Construction Milestones
Mobilization – Enabling / Fluid Dynamics January 26, 2026
Mobilization – Phase 1 June 12, 2026
Fluid Dynamics Turn-over August 4, 2026
Phase 1 Re-Open Brooks Street Entrance April 8, 2027
Phase 1 Turnover May 4, 2027
Phase 2 Turnover August 19, 2027
Building Full Weathertight October 14, 2027
Phase 3 Turnover / Substantial Completion December 1, 2027
Final Completion / Turn-over December 9, 2027