Facilities and Campus Operations

Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Phase 1

May 2026 –  January 2027
  • Brook Street Area to receive temporary fencing
  • Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC
  • Level 1 entrance to Prince Lab will remain open at this time until further notice
  • Fire lane will be shut down for tie-in work to street

Construction Logistics Hope St. – Enabling & Fluid Dynamics

May 2026 –  December 2027
  • Hope Street parking lot to receive updated Phase 1 temporary fencing
  • Traffic pattern to adjust to one way from Brook Street

**Note – Minden Hall work by another CM will also be occurring**

Construction Updates

Please note, scope may change based on existing conditions found in the field.

OCTOBER 2026 

Week of October 5, 2026
•Level 01 – Continue installation of Sprinkler branch piping throughout Level 1
•Level 01 – Investigate for low voltage / tel-data branch lines from cable tray (Caretta, Guduru and Peterson Spaces)
•Level 01 – Fire alarm rework and make safe in restrooms
•Level 01 – Demolish slab and excavate at existing restrooms
•Level 01 – Demolish existing concrete block at duct riser (pending exhaust tie-in OCL walkthrough)
•Level 01 – Relocate MEPs at new elevator location
•Level 01 – Mechanical make-safe in Rooms 106 / 108 (pending Lab Safe Entry Form approval)
•Level 02 – Build fire rated shaft around duct riser
•Level 02 – Continue structural steel at columns
•Level 02 – Form underside of roof vents to be closed up
•Level 03 – Install mezzanine steel and supports
•Roof – Install steel and temporary protection
•Roof – Penthouse demolition above mezzanine steel work
•Exterior – Sawcut brick and CMU at south façade for new window openings
 
Week of October 12, 2026
•Level 01 – Continue installation of Sprinkler branch piping throughout Level 1
•Level 01 – Under-slab plumbing re-work at restrooms
•Level 01 – Misc. demolition and make-safe for Material Science Lab and Fluid Dynamics    Conference Room buildout
•Level 01 – Excavate and underpin for new elevator pit
•Level 02 – Build fire rated shaft around duct riser
•Level 02 – Continue structural steel beams and columns install
•Level 02 – Form underside of roof vents to be closed up
•Level 03 – Install mezzanine steel and supports
•Roof – Install steel and temporary protection
•Roof – Penthouse demolition above mezzanine steel work
•Exterior – Tooth-in jamb CMU blocking and grout
•Exterior – Excavate and prepare for rain leader tie-in
 
Week of October 19, 2026
•Level 01 – Continue installation of Sprinkler branch piping throughout level 1
•Level 01 – Rough plumbing inspection of restrooms
•Level 01 – Pour new restroom floor slab
•Level 01 – MEP rough above ceiling in restrooms
•Level 01 – Misc. demolition and make-safe for Material Science Lab and Fluid Dynamics Conference Room buildout
•Level 01 – Excavate and underpin for new elevator pit
•Level 03 – Deck / detail / plumb mezzanine steel
•Roof – Misc. roof top prep work for steel and mechanical equipment
•Exterior – Install steel framing at CW openings

Construction Milestones

Mobilization – Enabling / Fluid Dynamics                            January 26, 2026
Mobilization – Phase 1                                                           June 12, 2026
Fluid Dynamics Turn-over                                                     August 4, 2026
Phase 1 Re-Open Brooks Street Entrance                              April 8, 2027
Phase 1 Turnover                                                                    May 4, 2027
Phase 2 Turnover                                                                    August 19, 2027
Building Full Weathertight                                                     October 14, 2027
Phase 3 Turnover / Substantial Completion                           December 1, 2027
Final Completion / Turn-over                                                 December 9, 2027