Construction Closure Overview
Construction Logistics Brook St. – Enabling & Fluid Dynamics
- January 2026 – May 2026
- No Changes to Brook Street Area
Construction Logistics Hope St. – Enabling & Fluid Dynamics
- Fire lane to remain open – daily work at North stair
- Brown dumpsters to be relocated / worked with construction laydown area
- Stair tower to be installed next to building for construction access inside temporary fence enclosure
- Loading dock access to be coordinated with Brown
Construction Updates
Please note, scope may change based on existing conditions found in the field.
MARCH 2026
Week of March 2, 2026
- Reconnaissance and exploratory through LIDH building
- SDC Office Construction – Install split systems, amenities ordered and being delivered for install
- Mechanical, plumbing, electrical & fire alarm reconnaissance and exploratory through LIDH Building
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) demolition & MEP layout
- B&H 503, 505, 507 (Lin Lab) demolition, MEP removal, etc.
- LIDH 111, 112 (Caretta Lab) demolition, MEP removal, etc. & sawcutting slab
- Enabling stair exterior north side lay out
- LIDH - Relocate electrical and fire alarm conduits where possible – level 1
- LIDH – Layout sprinkler piping throughout level 1
- Relocate electrical and fire alarm conduits where possible
- Layout sprinkler piping throughout level 1
Week of March 9, 2026
- Mechanical, plumbing, electrical & fire alarm reconnaissance and exploratory through LIDH Building
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) framing & electrical rough
- B&H 503, 505, 507 (Lin Lab) infill slabs, wall framing, piping install
- LIDH 111, 112 (Caretta Lab) runs in slab, infill slab, door infills, wall layout
- Enabling stair exterior north side lay out
- LIDH - relocate electrical and fire alarm conduits where possible – level 1
- LIDH – layoutsSprinkler piping throughout level 1
- Enabling stair exterior north side demo
- Relocate electrical and fire alarm conduits where possible
- Layout sprinkler piping throughout level 1
Week of March 16, 2026
- Mechanical, plumbing, electrical & fire alarm reconnaissance and exploratory through LIDH building
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) rough-in & electrical layout
- Relocate existing electrical and fire alarm conduits on column line D
- Steel infill and column work field measuring & layout on column Line D
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) - install sprinkler branch lines
- LIDH - install sprinkler main in level 1 corridor
- LIDH 111, 112 (Caretta Lab) wall framing & MEP rough-in
- B&H 503, 505, 507 (Lin Lab) MEP rough-in
Construction Milestones
Mobilization – Enabling / Fluid Dynamics - January 26, 2026
Fluid Dynamics Turn-over - June 4, 2026
Mobilization – Phase 1 - June 12, 2026
Phase 1 Re-Open Hope Street Entrance - April 8, 2027
Phase 1 Turnover - May 4, 2027
Phase 2 Turnover - August 19, 2027
Building Full Weathertight - October 14, 2027
Phase 3 Turnover / Substantial Completion - December 1, 2027
Final Completion / Turn-over - December 9, 2027