Construction Closure Overview
Construction Logistics Brook St. – Phase 1
May 2026 – January 2027
- Brook Street Area to receive temporary fencing
- Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC.
- Brook Street walkway to ERC will close August 1
- Level 1 entrance to Prince Lab will remain open at this time until further notice
- Fire lane will be shut down for tie-in work to street
Construction Logistics Hope St. – Enabling & Fluid Dynamics
May 2026 – December 2027
- Hope Street parking lot to receive updated Phase 1 temporary fencing
- Traffic pattern to adjust to one way from Brook Street
**Note – Minden Hall work by another CM will also be occurring**
Construction Updates
Please note, scope may change based on existing conditions found in the field.
AUGUST 2026
Week of August 3, 2026
- LIDH L01 – Continue installation of sprinkler branch piping throughout level 1
- LIDH L01 – Dual temp. piping removal & replacement
- LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
- LIDH South Exterior – Install remainder of site fence at the ERC walkway
- LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
- LIDH L02 – Select abatement and demolition of air handling units
- LIDH L02 – Build scaffolding and containment for remaining air handling units
- LIDH L02 & L03 – MEP make-safe
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Fume hood and equipment start-up and testing
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Move in client furniture
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Owner occupying space
Week of August 10, 2026
- LIDH L01 – Continue installation of sprinkler branch piping throughout level 1
- LIDH L01 – Dual temp. piping removal & replacement
- LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
- LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
- LIDH L02 – Select abatement and demolition of air handling units
- LIDH L02 & L03 – MEP make-safe
Week of August 17, 2026
- LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
- LIDH L01 – Dual temp. piping removal & replacement
- LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
- LIDH L02 – Swing Space electrical prep, plumbing venting tie-in & floor box work
- LIDH L02 – Select abatement and demolition of air handling units
- LIDH L02 & L03 – MEP make-safe
Construction Milestones
Mobilization – Enabling / Fluid Dynamics January 26, 2026
Mobilization – Phase 1 June 12, 2026
Fluid Dynamics Turn-over August 4, 2026
Phase 1 Re-Open Brooks Street Entrance April 8, 2027
Phase 1 Turnover May 4, 2027
Phase 2 Turnover August 19, 2027
Building Full Weathertight October 14, 2027
Phase 3 Turnover / Substantial Completion December 1, 2027
Final Completion / Turn-over December 9, 2027