Construction Closure Overview
Construction Logistics Brook St. – Enabling & Fluid Dynamics
- January 2026 – May 2026
- No Changes to Brook Street Area
Construction Logistics Hope St. – Enabling & Fluid Dynamics
- January 2026 – May 2026
- Fire lane to remain open – daily work at North stair
- Brown dumpsters to be relocated / worked with construction laydown area
- Stair tower to be installed next to building for construction access inside temporary fence enclosure
- Loading dock access to be coordinated with Brown
Construction Updates
Please note, scope may change based on existing conditions found in the field.
APRIL 2026
Week of April 13, 2026
- LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance throughout building
- LIDH - **ALL ROOMS LEVEL 1 – Construction team entering rooms for exploratory**
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue MEP rough-in
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – MEP inspections
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Top of walls with drywall
- LIDH 102B – Top off drywall, firestop & install ceiling
- LIDH Exterior – North stair – excavate for footings
Week of April 20, 2026
- LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance throughout building
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue MEP rough-in & tie-into existing systems
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Continue topping off walls (drywall)
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Layout ceiling
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – MEP inspections
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Flooring self leveler
- LIDH Exterior – Install north terrace stairs
- LIDH 102B – Painting
- LIDH 102B – Install flooring
Week of April 27, 2026
- LIDH - Mechanical, plumbing & electrical / fire alarm, low voltage reconnaissance throughout building
- LIDH Enabling L01 – Continue installation of sprinkler piping throughout level 1
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Overhead MEP & lighting installation
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Drywall walls
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Layout ceiling grid
- LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Paint 1st coat on walls
- LIDH 132 – Install ceiling grid
Construction Milestones
Mobilization – Enabling / Fluid Dynamics - January 26, 2026
Fluid Dynamics Turn-over - June 4, 2026
Mobilization – Phase 1 - June 12, 2026
Phase 1 Re-Open Hope Street Entrance - April 8, 2027
Phase 1 Turnover - May 4, 2027
Phase 2 Turnover - August 19, 2027
Building Full Weathertight - October 14, 2027
Phase 3 Turnover / Substantial Completion - December 1, 2027
Final Completion / Turn-over - December 9, 2027