Facilities and Campus Operations

Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Phase 1

May 2026 –  January 2027
  • Brook Street Area to receive temporary fencing
  • Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC.
  • Brook Street walkway to ERC will close August 1
  • Level 1 entrance to Prince Lab will remain open at this time until further notice
  • Fire lane will be shut down for tie-in work to street

Construction Logistics Hope St. – Enabling & Fluid Dynamics

May 2026 –  December 2027
  • Hope Street parking lot to receive updated Phase 1 temporary fencing
  • Traffic pattern to adjust to one way from Brook Street

**Note – Minden Hall work by another CM will also be occurring**

Construction Updates

Please note, scope may change based on existing conditions found in the field.

AUGUST  2026 

Week of August 3, 2026

  • LIDH L01 – Continue installation of sprinkler branch piping throughout level 1
  • LIDH L01 – Dual temp. piping removal & replacement
  • LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
  • LIDH South Exterior – Install remainder of site fence at the ERC walkway
  • LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
  • LIDH L02 – Select abatement and demolition of air handling units
  • LIDH L02 – Build scaffolding and containment for remaining air handling units
  • LIDH L02 & L03 – MEP make-safe
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Fume hood and equipment start-up and testing
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Move in client furniture
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Owner occupying space

Week of August 10, 2026

  • LIDH L01 – Continue installation of sprinkler branch piping throughout level 1
  • LIDH L01 – Dual temp. piping removal & replacement
  • LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
  • LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
  • LIDH L02 – Select abatement and demolition of air handling units
  • LIDH L02 & L03 – MEP make-safe

Week of August 17, 2026

  • LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
  • LIDH L01 – Dual temp. piping removal & replacement
  • LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
  • LIDH L02 – Swing Space electrical prep, plumbing venting tie-in & floor box work
  • LIDH L02 – Select abatement and demolition of air handling units
  • LIDH L02 & L03 – MEP make-safe
 

Construction Milestones

Mobilization – Enabling / Fluid Dynamics                            January 26, 2026
Mobilization – Phase 1                                                           June 12, 2026
Fluid Dynamics Turn-over                                                     August 4, 2026
Phase 1 Re-Open Brooks Street Entrance                              April 8, 2027
Phase 1 Turnover                                                                    May 4, 2027
Phase 2 Turnover                                                                    August 19, 2027
Building Full Weathertight                                                     October 14, 2027
Phase 3 Turnover / Substantial Completion                           December 1, 2027
Final Completion / Turn-over                                                 December 9, 2027