Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Phase 1

May 2026 –  January 2027
  • Brook Street Area to receive temporary fencing
  • Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC
  • Level 1 entrance to Prince Lab will remain open at this time until further notice
  • Fire lane will be shut down for tie-in work to street

Construction Logistics Hope St. – Enabling & Fluid Dynamics

May 2026 –  December 2027
  • Hope Street parking lot to receive updated Phase 1 temporary fencing
  • Traffic pattern to adjust to one way from Brook Street

**Note – Minden Hall work by another CM will also be occurring**

Construction Updates

Please note, scope may change based on existing conditions found in the field.

JULY 2026 

Week of July 6, 2026

•LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 – Complete exhaust duct tie-in work
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP Make-safe
•LIDH L02 & L03 – Scaffolding shoring for slab at mezzanine
•LIDH L02 & L03 – Ongoing fire alarm work to enable construction
•LIDH Fire Lane – Camera work to Brook Street
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Punchlist, paint touch up, and final cleaning
 
Week of July 13, 2026
•LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP make-safe
•LIDH L02 & L03 – Ongoing fire alarm work to enable construction
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Fume hood and equipment start-up and testing
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Move in client furniture
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Owner occupying space July 17th
 
Week of July 20, 2026
•LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP make-safe
•LIDH L02 & L03 – Ongoing fire alarm work to enable construction
 

Construction Milestones

Mobilization – Enabling / Fluid Dynamics  January 26, 2026
Mobilization – Phase 1  June 12, 2026
Fluid Dynamics Turn-over   July 17, 2026
Phase 1 Re-Open Brooks Street Entrance  April 8, 2027
Phase 1 Turnover  May 4, 2027
Phase 2 Turnover  August 19, 2027
Building Full Weathertight    October 14, 2027
Phase 3 Turnover / Substantial Completion  December 1, 2027
Final Completion / Turn-over    December 9, 2027