Facilities and Campus Operations

Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Enabling & Fluid Dynamics

  • January 2026 – May 2026
    • No Changes to Brook Street Area

Construction Logistics Hope St. – Enabling & Fluid Dynamics

  • January 2026 – May 2026
    • Fire lane to remain open – daily work at North stair
    • Brown dumpsters to be relocated / worked with construction laydown area
    • Stair tower to be installed next to building for construction access inside temporary fence enclosure
    • Loading dock access to be coordinated with Brown

Construction Updates

Please note, scope may change based on existing conditions found in the field.Week of February 16, 202

Week of February 9, 2026

  • SDC Office Construction at LIDH Mezzanine Mechanical Space
  • Electrical & Fire Alarm Reconnaissance and exploratory through LIDH Building
  • Mechanical Reconnaissance and exploratory through LIDH Building
  • Plumbing Reconnaissance and exploratory through LIDH Building
  • Low Voltage / Tel / Data reconnaissance and exploratory through LIDH Building
  • Set up exterior fencing per logistics at Hope Street parking lot

Week of February 16, 2026

  • Site Closed Monday 2/16 for President’s Day
  • SDC Office Construction at LIDH Mezzanine Mechanical Space
  • Electrical & Fire Alarm Reconnaissance and exploratory through LIDH Building
  • Mechanical Reconnaissance and exploratory through LIDH Building
  • Plumbing Reconnaissance and exploratory through LIDH Building
  • Low Voltage / Tel / Data reconnaissance and exploratory through LIDH Building
  • Fluid Dynamics abatement / demolition
  • Exterior north stair at fire lane enabling work – layout and demolition

Week of February 23, 2026

  • SDC Office Construction at LIDH Mezzanine Mechanical Space
  • Electrical & Fire Alarm Reconnaissance and exploratory through LIDH Building
  • Mechanical Reconnaissance and exploratory through LIDH Building
  • Plumbing Reconnaissance and exploratory through LIDH Building
  • Low Voltage / Tel / Data Reconnaissance and exploratory through LIDH Building
  • Fluid Dynamics demolition
  • Exterior north stair at fire lane enabling work

Construction Milestones

Mobilization – Enabling / Fluid Dynamics - January 26, 2026

Fluid Dynamics Turn-over - June 4, 2026

Mobilization – Phase 1 - June 12, 2026

Phase 1 Re-Open Hope Street Entrance - April 8, 2027

Phase 1 Turnover - May 4, 2027

Phase 2 Turnover - August 19, 2027

Building Full Weathertight - October 14, 2027

Phase 3 Turnover / Substantial Completion - December 1, 2027

Final Completion / Turn-over - December 9, 2027