Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Phase 1

May 2026 –  January 2027
  • Brook Street Area to receive temporary fencing
  • Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC
  • Level 1 entrance to Prince Lab will remain open at this time until further notice
  • Fire lane will be shut down for tie-in work to street

Construction Logistics Hope St. – Enabling & Fluid Dynamics

May 2026 –  December 2027
  • Hope Street parking lot to receive updated Phase 1 temporary fencing
  • Traffic pattern to adjust to one way from Brook Street

**Note – Minden Hall work by another CM will also be occurring**

Construction Updates

Please note, scope may change based on existing conditions found in the field.

SEPTEMBER  2026 

Week of September 14, 2026

•LIDH L01 – Continue installation of Sprinkler branch piping throughout level 1
•LIDH L01 – Dual Temp. Piping Removal & Replacement
•Investigate for low voltage / tel-data branch lines from cable tray (Caretta, Guduru and Peterson Spaces)
•LIDH L01 - Men's & Women's Restroom Officially Offline
•LIDH L01 – MEP demolition at existing restrooms
•LIDH L01 – Demolish existing concrete block at duct riser (pending OCL approval)
•LIDH L01 – Relocate EH&S mop sink and emergency eye wash station
•LIDH L01 - Select Demolition for conduit runs (Rooms 124, 113B, 113A, 113, 127, 106C, 106, 141)
•LIDH L02 – Demolition of rooms below south mezzanine
•LIDH L02 – Continue structural steel at columns
•LIDH L02 – Stair 2 make-safe for demolition
•LIDH L03 – Existing steel guardrail and column demolition
•LIDH Exterior – South masonry wall exploratory demolition
 

Week of September 21, 2026

•LIDH L01 – Continue installation of Sprinkler branch piping throughout level 1
•LIDH L01 – Dual Temp. Piping Removal & Replacement
•LIDH L01 - Investigate for low voltage / tel-data branch lines from cable tray (Caretta, Guduru and Peterson Spaces)
•LIDH L01 – Demolition of existing restrooms
•LIDH L02 – Demolition of rooms below south mezzanine
•LIDH L02 – Continue structural steel at columns
•LIDH L02 – Demolition of Stair 2 at south mezzanine
•LIDH Exterior – South masonry wall exploratory demolition

Week of September 28, 2026

•LIDH All Levels – Fire Alarm Control Panel Switch-over Testing – 4 hours from 3:00 PM – 7:00 PM +/- - specific day TBD
•LIDH L01 – Continue installation of Sprinkler branch piping throughout level 1
•LIDH L01 – Dual Temp. Piping Removal & Replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable tray
•LIDH L01 – Install new temporary construction barricades for restroom renovation
•LIDH L01 – Demolition of walls and slabs for underpinning and new elevator pit (pending Fire Alarm Panel relocation)
•LIDH L02 – Demolition of rooms below south mezzanine
•LIDH L02 – Continue structural steel at columns
•LIDH L02 – Demolition of Stair 2 at south mezzanine
•LIDH Exterior – Install steel weatherproof barricades at south façade

Construction Milestones

Mobilization – Enabling / Fluid Dynamics                            January 26, 2026
Mobilization – Phase 1                                                           June 12, 2026
Fluid Dynamics Turn-over                                                     August 4, 2026
Phase 1 Re-Open Brooks Street Entrance                              April 8, 2027
Phase 1 Turnover                                                                    May 4, 2027
Phase 2 Turnover                                                                    August 19, 2027
Building Full Weathertight                                                     October 14, 2027
Phase 3 Turnover / Substantial Completion                           December 1, 2027
Final Completion / Turn-over                                                 December 9, 2027