Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Enabling & Fluid Dynamics

  • January 2026 – May 2026
    • No Changes to Brook Street Area

Construction Logistics Hope St. – Enabling & Fluid Dynamics

  • Fire lane to remain open – daily work at North stair
  • Brown dumpsters to be relocated / worked with construction laydown area
  • Stair tower to be installed next to building for construction access inside temporary fence enclosure
  • Loading dock access to be coordinated with Brown

Construction Updates

Please note, scope may change based on existing conditions found in the field.

MARCH 2026

Week of March 2, 2026

  • Reconnaissance and exploratory through LIDH building
  • SDC Office Construction – Install split systems, amenities ordered and being delivered for install
  • Mechanical, plumbing, electrical & fire alarm reconnaissance and exploratory through LIDH Building
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) demolition & MEP layout
  • B&H 503, 505, 507 (Lin Lab) demolition, MEP removal, etc.
  • LIDH 111, 112 (Caretta Lab) demolition, MEP removal, etc. & sawcutting slab
  • Enabling stair exterior north side lay out
  • LIDH - Relocate electrical and fire alarm conduits where possible – level 1
  • LIDH – Layout sprinkler piping throughout level 1
  • Relocate electrical and fire alarm conduits where possible
  • Layout sprinkler piping throughout level 1

Week of March 9, 2026

  • Mechanical, plumbing, electrical & fire alarm reconnaissance and exploratory through LIDH Building
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) framing & electrical rough
  • B&H 503, 505, 507 (Lin Lab) infill slabs, wall framing, piping install
  • LIDH 111, 112 (Caretta Lab) runs in slab, infill slab, door infills, wall layout
  • Enabling stair exterior north side lay out
  • LIDH - relocate electrical and fire alarm conduits where possible – level 1
  • LIDH – layoutsSprinkler piping throughout level 1
  • Enabling stair exterior north side demo
  • Relocate electrical and fire alarm conduits where possible
  • Layout sprinkler piping throughout level 1

Week of March 16, 2026

  • Mechanical, plumbing, electrical & fire alarm reconnaissance and exploratory through LIDH building
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) rough-in & electrical layout
  • Relocate existing electrical and fire alarm conduits on column line D
  • Steel infill and column work field measuring & layout on column Line D
  • LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer)  - install sprinkler branch lines
  • LIDH - install sprinkler main in level 1 corridor
  • LIDH 111, 112 (Caretta Lab) wall framing & MEP rough-in
  • B&H 503, 505, 507 (Lin Lab) MEP rough-in

     

Construction Milestones

Mobilization – Enabling / Fluid Dynamics - January 26, 2026
Fluid Dynamics Turn-over - June 4, 2026
Mobilization – Phase 1 - June 12, 2026
Phase 1 Re-Open Hope Street Entrance - April 8, 2027
Phase 1 Turnover - May 4, 2027
Phase 2 Turnover - August 19, 2027
Building Full Weathertight - October 14, 2027
Phase 3 Turnover / Substantial Completion - December 1, 2027
Final Completion / Turn-over - December 9, 2027