Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Phase 1

May 2026 –  January 2027
  • Brook Street Area to receive temporary fencing
  • Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC
  • Level 1 entrance to Prince Lab will remain open at this time until further notice
  • Fire lane will be shut down for tie-in work to street

Construction Logistics Hope St. – Enabling & Fluid Dynamics

May 2026 –  December 2027
  • Hope Street parking lot to receive updated Phase 1 temporary fencing
  • Traffic pattern to adjust to one way from Brook Street

**Note – Minden Hall work by another CM will also be occurring**

Construction Updates

Please note, scope may change based on existing conditions found in the field.

November 2026

Week of November 16, 2026

  • Level 01 – Continue installation of Sprinkler branch piping throughout Level 1
  • Level 01 – Framing for new restrooms, Material Science Lab, and Fluid Dynamics Conference Room
  • Level 01 – Sawcut Fluid Dynamics Conference Room floor
  • Level 01 – Form and pour new elevator pit
  • Level 01 – Southwest stair re-work and demolition
  • Level 02 – Framing for new interior partitions
  • Level 03 – Clean, place, and cure new concrete slab on deck
  • Roof – Misc. rooftop prep work for steel and mechanical equipment
  • Exterior – Install curtain wall framing and glazing at south façade
  • Exterior – Form and place cooling tower concrete pad at north elevation
  • Exterior – Excavate for new concrete footings at west entrance

Week of November 23, 2026

  • Level 01 – Continue installation of Sprinkler branch piping throughout Level 1
  • Level 01 – Framing for new restrooms, Material Science Lab, and Fluid Dynamics Conference Room
  • Level 01 – Southwest stair re-work and demolition
  • Level 01 – Elevator Pit Work
  • Level 02 – Framing for new interior partitions
  • Level 03 – Framing for new interior partitions
  • Roof – Misc. rooftop prep work for steel and mechanical equipment
  • Exterior – Install curtain wall framing and glazing at south façade
  • Exterior – Excavate for new concrete footings at west entrance
 

Week of November 30, 2026

  • Level 01 – Continue installation of Sprinkler branch piping throughout Level 1
  • Level 01 – Framing for new restrooms, Material Science Lab, and Fluid Dynamics Conference Room
  • Level 01 – Elevator Pit Work
  • Level 01 – Southwest stair re-work and demolition
  • Level 02 – Framing for new interior partitions
  • Level 03 – Framing for new interior partitions
  • Roof – Misc. rooftop prep work for steel and mechanical equipment
  • Exterior – Install curtain wall framing and glazing at south façade
  • Exterior – Form and place cooling tower concrete pad at north elevation
  • Exterior – Excavate for new concrete footings at west entrance
     

Construction Milestones

Mobilization – Enabling / Fluid Dynamics                            January 26, 2026
Mobilization – Phase 1                                                              June 12, 2026
Fluid Dynamics Turn-over                                                      August 4, 2026
Phase 1 Re-Open Brooks Street Entrance                              May 13, 2027
Phase 1 Turnover                                                                       July 28, 2027
Building Full Weathertight                                                      November 19, 2027
Phase 2 Turnover / Substantial Completion                          December 22, 2027
Final Completion / Turn-over                                                 December 31, 2027