Construction Closure Overview
Construction Logistics Brook St. – Phase 1
May 2026 – January 2027
Brook Street Area to receive temporary fencing
Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC
Level 1 entrance to Prince Lab will remain open at this time until further notice
Fire lane will be shut down for tie-in work to street
Construction Logistics Hope St. – Enabling & Fluid Dynamics
May 2026 – December 2027
**Note – Minden Hall work by another CM will also be occurring**
![]()
Construction Updates
Please note, scope may change based on existing conditions found in the field.
JUNE 2026
Week of June 15, 2026
•LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Start installation of temporary wall tarps for Phase 1
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 – BDW space light demolition and power shut downs to BDW / JEPIS
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP make-safe
•LIDH Exterior – Stormwater system sitework and foundation exploratory
•LIDH Exterior – Brooks Street entrance covered walkway and Emergency Exit Only doors installed
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Finish paint touch ups in lab spaces
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Repair ACT ceiling and punchlist
Week of June 22, 2026
•LIDH L01 – Continue installation of Sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Start installation of temporary wall tarps for Phase 1
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 – BDW space light demolition and power shut downs to BDW / JEPIS
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP make-safe
•LIDH Exterior – Stormwater system sitework and foundation exploratory (if needed)
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Mechanical and electrical commissioning & start-up
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Install ceiling tiles
Week of June 29, 2026
•LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP make-safe
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Mechanical and electrical commissioning & start-up
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Frame fire rated soffit around exhaust duct risers
Construction Milestones
Mobilization – Enabling / Fluid Dynamics - January 26, 2026
Fluid Dynamics Turn-over - June 4, 2026
Mobilization – Phase 1 - June 12, 2026
Phase 1 Re-Open Hope Street Entrance - April 8, 2027
Phase 1 Turnover - May 4, 2027
Phase 2 Turnover - August 19, 2027
Building Full Weathertight - October 14, 2027
Phase 3 Turnover / Substantial Completion - December 1, 2027
Final Completion / Turn-over - December 9, 2027