Lassonde Innovation and Design Hub - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

Construction Logistics Brook St. – Phase 1

May 2026 –  January 2027
  • Brook Street Area to receive temporary fencing
  • Entrance to ERC will shift to the south entrance or up the stairs on the south side of the courtyard to the main entrance of ERC
  • Level 1 entrance to Prince Lab will remain open at this time until further notice
  • Fire lane will be shut down for tie-in work to street

Construction Logistics Hope St. – Enabling & Fluid Dynamics

May 2026 –  December 2027
  • Hope Street parking lot to receive updated Phase 1 temporary fencing
  • Traffic pattern to adjust to one way from Brook Street

**Note – Minden Hall work by another CM will also be occurring**

Construction Updates

Please note, scope may change based on existing conditions found in the field.

JUNE 2026 

Week of June 15, 2026

•LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Start installation of temporary wall tarps for Phase 1
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 – BDW space light demolition and power shut downs to BDW / JEPIS
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP make-safe
•LIDH Exterior – Stormwater system sitework and foundation exploratory
•LIDH Exterior – Brooks Street entrance covered walkway and Emergency Exit Only doors installed
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Finish paint touch ups in lab spaces
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Repair ACT ceiling and punchlist

Week of June 22, 2026

•LIDH L01 – Continue installation of Sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Start installation of temporary wall tarps for Phase 1
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 – BDW space light demolition and power shut downs to BDW / JEPIS
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP make-safe
•LIDH Exterior – Stormwater system sitework and foundation exploratory (if needed)
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Mechanical and electrical commissioning & start-up
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Install ceiling tiles
 
Week of June 29, 2026
•LIDH L01 – Continue installation of sprinkler branch piping throughout Level 1
•LIDH L01 – Dual temp. piping removal & replacement
•LIDH L01 – Investigate for low voltage / tel-data branch lines from cable
•LIDH L02 – Swing space electrical prep, plumbing venting tie-in & floor box work
•LIDH L02 & L03 – Demolition and select abatement scope
•LIDH L02 & L03 – MEP make-safe
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Mechanical and electrical commissioning & start-up
•LIDH 129, 130, 131, 134, 135, 137, 138 (Breuer) – Frame fire rated soffit around exhaust duct risers

Construction Milestones

Mobilization – Enabling / Fluid Dynamics - January 26, 2026
Fluid Dynamics Turn-over - June 4, 2026
Mobilization – Phase 1 - June 12, 2026
Phase 1 Re-Open Hope Street Entrance - April 8, 2027
Phase 1 Turnover - May 4, 2027
Phase 2 Turnover - August 19, 2027
Building Full Weathertight - October 14, 2027
Phase 3 Turnover / Substantial Completion - December 1, 2027
Final Completion / Turn-over - December 9, 2027