Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - March 27, 2026
- Elbow Street closed for bridge detailing

Construction Updates
Please note, scope may change based on existing conditions found in the field.
March/APRIL 2026
Week of March 23, 2026
- Roof flashing level 9 and 10
- Buildout switchgear level 9
- MEP equipment connections level 8
- Install final roof level 8
- Install flashings level 9 and 10
- In-wall rough level 7
- Framing level 7
- MEP overhead rough level 6
- Blocking, drywall, taping level 6
- Tape and paint level 5
- Install metal panel mezzanine level
- Prime and paint level 2
- MEP rough on level 1
- Install passenger and service elevators
- Install granite level 1
- AVB and Z-Girt loading dock
- Install site drainage structures and piping
- Metal panel exterior soffits
Week of March 30, 2026
- Buildout switchgear level 9
- MEP equipment connections level 8
- Buildout level 8 generator room
- Install final roof level 8
- Install flashings level 9 and 10
- In-wall rough and blocking level 7
- Framing level 7
- In-wall rough level 6
- Blocking, drywall, taping level 6
- Tape and paint level 5
- K-13 install level 5
- Install metal panel mezzanine level
- Install ceilings level 2
- MEP rough on level 1
- Install passenger and service elevators
- Install granite level 1
- Install site drainage structures and piping
- Metal panel exterior soffits
Week of April 6, 2026
- Buildout switchgear level 9
- MEP equipment connections level 8
- Buildout level 8 generator room
- Install final roof level 8
- In-wall rough and blocking level 7
- Framing level 7
- Blocking, drywall, taping level 6
- Tape and paint level 5
- K-13 install level 5
- Install metal panel mezzanine level
- Install ceilings level 2
- MEP rough on level 1
- Install passenger and service elevators
- Install granite level 1
- Install site drainage structures and piping
- Install fencing at electric yard
- Metal panel exterior soffit