Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offlin
  • May 26th thru July 1st Elbow Street for sidewalk installation
  • May 26th thru August 31st Richmond Street northbound closed for landscaping/sidewalk install
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

June 2026

Week of June 1, 2026

  • Test wire and breakers level 9
  • Test and insulate MEP equipment level 9
  • Install panels and control wiring level 8
  • Install valves level 8
  • Final MEP connections level 8
  • In-wall rough and blocking level 7
  • Sheetrock level 7
  • Overhead rough/insulation level 7
  • Chilled beam install and insulation level 6
  • Bathroom tile level 6
  • Painting level 6
  • Install flooring level 5
  • Ceiling install level 5
  • Lab casework level 5
  • Moisture mitigation level 2
  • MEP rough on level 1
  • Framing, insulation, and in-wall rough level 1
  • Install passenger and service elevators
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut Street and Elbow Street
  • Form and pour walls at Gate C
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building

Week of June 8, 2026

  • Power and lighting level 9
  • Test and insulate MEP equipment level 9
  • Install panels and control wiring level 8
  • Fill and flush equipment level 8
  • Start-up AHU
  • Taping level 7
  • Sheetrock level 7
  • Overhead rough/insulation level 7
  • Chilled beam install and insulation level 6
  • Bathroom tile level 6
  • Painting level 6
  • Install flooring level 5
  • Lab casework level 5
  • MEP rough on level 1
  • Fire stopping level 1
  • Framing, insulation, and in-wall rough level 1
  • Install passenger and service elevators
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut Street and Elbow Street
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building

Week of June 15, 2026

  • Site closed Friday, June 19th for Juneteenth
  • Power and lighting level 9
  • Test and insulate MEP equipment level 9
  • Install panels and control wiring level 8
  • Fill and flush equipment level 8
  • Taping level 7
  • Sheetrock level 7
  • Overhead rough/insulation level 7
  • Install flooring level 6
  • Bathroom tile level 6
  • Painting level 6
  • Install flooring level 5
  • Lab casework level 5
  • MEP rough on level 1
  • Drywall level 1
  • Install passenger and service elevators
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut Street and Elbow Street
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building