Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline

Construction Updates
Please note, scope may change based on existing conditions found in the field.
November 2026
Week of November 16, 2026
- Fire Alarm Programing and Testing
- Balancing
- Start-Up and Commissioning of Equipment
- Install Control Wiring Level 8
- Tel-Data / Security Level 8
- Doors and Frame Install Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Base Level 6
- Finish Hub and Bathroom Level 6
- Rough Clean Level 6
- Complete Bathrooms Level 5
- Complete Hub Ceiling Level 5
- Polished Concrete Level 1
- Millwork Install Level 1
- Ceiling Level 1
- Loading Dock Equipment Install
- Landscape along Elm St
- Granite Seawall and Bench Install
Week of November 23, 2026
- Site Closed Thursday 11/26 for Thanksgiving
- Fire Alarm Programing and Testing
- Balancing
- Start-Up and Commissioning of Equipment
- Install Control Wiring Level 8
- Tel-Data / Security Level 8
- Doors and Frame Install Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Finish Hub and Bathroom Level 6
- Complete Bathrooms Level 5
- Complete Hub Ceiling Level 5
- Polished Concrete Level 1
- Millwork Install Level 1
- Casework Level 1
- Landscape along Elm St
- Granite Seawall and Bench Install
Week of November 30, 2026
- Fire Alarm Programing and Testing
- Balancing
- Start-Up and Commissioning of Equipment
- Install Control Wiring Level 8
- Tel-Data / Security Level 8
- Doors and Frame Install Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Rough Clean Level 6
- Complete Bathrooms Level 6
- Complete Hub Millwork Level 5 and 6
- Millwork Install Level 1
- Casework Level 1
- Landscape along Elm St
- Granite Seawall and Bench Install