Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
  • May 26th thru June 30th    Elbow Street for sidewalk installation
  • June 8th thru September 6th  Richmond Street northbound closed for landscaping/sidewalk install
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

JuLY 2026
Week of July 13, 2026
  • Test and insulate MEP equipment Level 9
  • Fire alarm Level 9
  • Install valves and control wiring Level 8
  • Terminate electrical panels Level 8
  • Taping Level 7
  • Frame and drywall hard ceilings Level 7
  • Epoxy walls and floors Level 7
  • Overhead rough/insulation Level 7
  • Install flooring Level 6
  • Lab casework install Level 6
  • Painting Level 6
  • Ceiling install Level 6
  • Lab casework Level 5
  • Install glass partitions Level 5
  • Drywall and taping Level 1
  • In-wall inspections Level 1
  • AV rack install Level 1
  • Install passenger and jump elevator
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow Streets
  • Cox relocation of conduit
  • Landscaping along Richmond Street
  • Construction hoist removal and infill

Week of July 20, 2026

  • Test and insulate MEP equipment Level 9
  • Fire alarm Level 9
  • Install valves and control wiring Level 8
  • Terminate electrical panels Level 8
  • Taping Level 7
  • Frame and drywall hard ceilings Level 7
  • Epoxy walls and floors Level 7
  • Overhead rough/insulation Level 7
  • Install flooring Level 6
  • Lab casework install Level 6
  • Install glass partitions Level 5
  • Drywall and taping Level 1
  • In-wall inspections Level 1
  • AV rack install Level 1
  • Install passenger and jump elevator
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow Streets
  • Cox relocation of conduit
  • Landscaping along Richmond Street
  • Construction hoist removal and infill
Week of July 27, 2026
  • Test and insulate MEP equipment Level 9
  • Fire alarm Level 9
  • Install valves and control wiring Level 8
  • Terminate electrical panels Level 8
  • Taping Level 7
  • Frame and drywall hard ceilings Level 7
  • Epoxy walls and floors Level 7
  • Overhead rough/insulation Level 7
  • Install flooring Level 6
  • Lab casework install Level 6
  • Polished concrete Level 5
  • Install fabric panels Level 5
  • Drywall and taping Level 1
  • In-wall inspections Level 1
  • AV rack install Level 1
  • Install passenger and jump elevator
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow Streets
  • Cox relocation of conduit
  • Landscaping along Richmond Street
  • Construction hoist removal and infill