William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - May 30, 2026
  • Elbow Street closed for bridge detailing

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

APRIL 2026

Week of April 13, 2026

  • Finish install level 8 Roof and 9/10 flashings
  • Buildout switchgear level 9
  • MEP equipment connections level 8
  • Buildout level 8 generator room
  • In-wall rough level 7
  • Overhead rough level 7
  • Drywall and taping level 6
  • Overhead rough level 6
  • Paint level 5
  • Install ceilings and chilled beams level 5
  • Bathroom tile level 5
  • Install ceilings level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Metal panel exterior soffit


Week of April 20, 2026

  • Buildout switchgear level 9
  • In-wall rough and blocking level 7
  • Overhead rough/insulation level 7
  • Taping level 6
  • K-13 install level 5
  • Bathroom tile level 5
  • Paint level 5
  • Install ceilings and chilled beams level 5
  • Install K-13 level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Install fencing at electric yard
  • Start landscaping on western side of site


Week of April 27, 2026
 

  • Buildout switchgear level 9
  • In-wall rough and blocking level 7
  • Overhead rough/insulation level 7
  • Drywall level 7
  • Tape and paint level 6
  • K-13 level 6
  • Bathroom tile level 5
  • Install ceilings and chilled beams level 5
  • Install K-13 level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Install fencing at electric yard
  • Start landscaping on western side of site