Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offlin
- May 26th thru July 1st Elbow Street for sidewalk installation
- May 26th thru August 31st Richmond Street northbound closed for landscaping/sidewalk install

Construction Updates
Please note, scope may change based on existing conditions found in the field.
June 2026
Week of June 1, 2026
- Test wire and breakers level 9
- Test and insulate MEP equipment level 9
- Install panels and control wiring level 8
- Install valves level 8
- Final MEP connections level 8
- In-wall rough and blocking level 7
- Sheetrock level 7
- Overhead rough/insulation level 7
- Chilled beam install and insulation level 6
- Bathroom tile level 6
- Painting level 6
- Install flooring level 5
- Ceiling install level 5
- Lab casework level 5
- Moisture mitigation level 2
- MEP rough on level 1
- Framing, insulation, and in-wall rough level 1
- Install passenger and service elevators
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut Street and Elbow Street
- Form and pour walls at Gate C
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building
Week of June 8, 2026
- Power and lighting level 9
- Test and insulate MEP equipment level 9
- Install panels and control wiring level 8
- Fill and flush equipment level 8
- Start-up AHU
- Taping level 7
- Sheetrock level 7
- Overhead rough/insulation level 7
- Chilled beam install and insulation level 6
- Bathroom tile level 6
- Painting level 6
- Install flooring level 5
- Lab casework level 5
- MEP rough on level 1
- Fire stopping level 1
- Framing, insulation, and in-wall rough level 1
- Install passenger and service elevators
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut Street and Elbow Street
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building
Week of June 15, 2026
- Site closed Friday, June 19th for Juneteenth
- Power and lighting level 9
- Test and insulate MEP equipment level 9
- Install panels and control wiring level 8
- Fill and flush equipment level 8
- Taping level 7
- Sheetrock level 7
- Overhead rough/insulation level 7
- Install flooring level 6
- Bathroom tile level 6
- Painting level 6
- Install flooring level 5
- Lab casework level 5
- MEP rough on level 1
- Drywall level 1
- Install passenger and service elevators
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut Street and Elbow Street
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building