Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline

Construction Updates
Please note, scope may change based on existing conditions found in the field.
October/November 2026
Week of October 26, 2026
- Insulate Level 9
- Install Valves and Control Wiring Level 8
- MEP Connection Level 8
- Epoxy Walls and Floors Level 7
- Doors and Frame Install Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Lab Equipment Install Level 7
- Base Install Level 6
- Finishes by Hoist Infill Level 5
- Carpet Level 2
- Polished Concrete Level 1
- Flooring Level 1
- Paint Level 1
- Aluminum Frame Install Level 1
- Form and Pour Site Sidewalks
- Landscaping Along Richmond St
- Granite Seawall and Bench Install
Week of November 2, 2026
- Test and Insulate Equipment Level 9
- Install Control Wiring Level 8
- MEP Connection Level 8
- Epoxy Walls and Floors Level 7
- Doors and Frame Install Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Rough Clean Level 6
- Punchlist Level 5
- Rough Clean Level 2
- Polished Concrete Level 1
- Casework Install Level 1
- Paint Level 1
- Aluminum Frame Install Level 1
- Form and Pour Site Sidewalks
- Granite Seawall and Bench Install
Week of November 9, 2026
- Site Closed Wednesday 11/11 for Veteran’s Day
- Electrical Install and MEP Finishes Level 9
- Install Control Wiring Level 8
- MEP Connections and Balancing Level 8
- Lab Equipment Install Level 7
- Doors and Frame Install Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Under Cabinet Casework Install Level 6
- Rough Clean Level 6
- Punchlist Level 5
- Rough Clean Level 2
- Polished Concrete Level 1
- Casework Install Level 1
- Paint Level 1
- Millwork Install Level 1
- Form and Pour Site Sidewalks
- Granite Seawall and Bench Install