William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - March 27, 2026
  • Elbow Street closed for bridge detailing
March 12 thru March 15
•Elbow and Chestnut Street closed 6 AM thru 7 PM for tower crane removal

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

 March 2026

Week of March 9, 2026

  • Roof flashing levels 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Build switchgear level 9 
  • Install grating at level 9 dunnage
  • Frame and sheath exterior walls level 9
  • Install roofing level 8
  • Rig and set plumbing equipment level 8
  • Framing and MEP rough level 7
  • Framing level 7
  • MEP overhead and in-wall rough 6
  • Drywall level 6
  • Drywall, taping, painting level 5
  • Install metal panel level 4 north
  • Prime and paint level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service elevators
  • Install granite level 1
  • Take down tower crane March 12th to 15th (5 AM to 7 PM)

    Week of March 16, 2026

  • Roof flashing levels 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Frame and sheath exterior walls level 9
  • MEP equipment connections level 8
  • Install flashings level 9 and 10
  • In-wall rough and blocking level 7
  • Framing level 7
  • Blocking, drywall and taping level 6
  • Taping and painting level 5
  • Install K-13 level 5
  • Install metal panel mezzanine level
  • Prime and paint level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Install fencing at electric yard


Week of March 23, 2026

  • Install roofing at level 8 plenum
  • Build out generator room level 8
  • Framing, in-wall rough, and in-wall inspection level 7
  • Overhead MEP rough level 7
  • Drywall and taping level 6
  • Taping and painting level 5
  • Install K-13 level 5
  • Install metal panel mezzanine level
  • Prime and paint level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Install fencing at electric yard
  • Install light pole bases