William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

October/November 2026

Week of October 26, 2026

  • Insulate Level 9
  • Install Valves and Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Lab Equipment Install Level 7
  • Base Install Level 6
  • Finishes by Hoist Infill Level 5
  • Carpet Level 2
  • Polished Concrete Level 1
  • Flooring Level 1
  • Paint Level 1
  • Aluminum Frame Install Level 1
  • Form and Pour Site Sidewalks
  • Landscaping Along Richmond St
  • Granite Seawall and Bench Install

Week of November 2, 2026

  • Test and Insulate Equipment Level 9
  • Install Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Rough Clean Level 6
  • Punchlist Level 5
  • Rough Clean Level 2
  • Polished Concrete Level 1
  • Casework Install Level 1
  • Paint Level 1
  • Aluminum Frame Install Level 1
  • Form and Pour Site Sidewalks
  • Granite Seawall and Bench Install

Week of November 9, 2026

  • Site Closed Wednesday 11/11 for Veteran’s Day
  • Electrical Install and MEP Finishes Level 9
  • Install Control Wiring Level 8
  • MEP Connections and Balancing Level 8
  • Lab Equipment Install Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Under Cabinet Casework Install Level 6
  • Rough Clean Level 6
  • Punchlist Level 5
  • Rough Clean Level 2
  • Polished Concrete Level 1
  • Casework Install Level 1
  • Paint Level 1
  • Millwork Install Level 1
  • Form and Pour Site Sidewalks
  • Granite Seawall and Bench Install