Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
  • June 8 thru October 3 Richmond Street northbound closed for landscaping/sidewalk install
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

October 2026

Week of October 5, 2026
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Carpet Install Level 6
  • Ceiling Install Level 6
  • Final Paint Level 6
  • Base Install Level 5
  • Final Paint Level 5
  • Glass Wall Install Level 5
  • Ceiling Install Level 1
  • Painting Level 1
  • Flooring Level 1
  • Form and Pour Site Sidewalks
  • Landscaping Along Richmond Street
  • Granite Seawall and Bench Install
Week of October 12, 2026
  • Site Closed Monday 10/12
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Carpet Install Level 6
  • Glass Wall Install Level 6
  • Rough Clean Level 5
  • Glass Wall Install Level 5
  • Final Paint Level 2
  • Polished Concrete Level 1
  • Flooring Level 1
  • Form and Pour Site Sidewalks
  • Landscaping Along Richmond Street
  • Granite Seawall and Bench Install
Week of October 19, 2026
  • Power and Lighting Level 9
  • Terminate Panels and Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Base Install Level 6
  • Glass Wall Install Level 6
  • Rough Clean Level 5
  • Final Paint and Carpet Level 2
  • Polished Concrete Level 1
  • Flooring Level 1
  • Form and Pour Site Sidewalks
  • Landscaping Along Richmond Street
  • Granite Seawall and Bench Install