Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - February 27, 2026
  • Elbow Street closed for bridge detailing


 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

 January/February 2026


Week of January 19, 2026

  • MEP install level 10
  • Rig and set AHU and plumbing equipment level 8
  • Build switchgear level 9
  • Run conduit for switchgear from 1 to 9
  • Curtainwall install 1, 8 and 9
  • Low pressure ductwork level 7
  • Epoxy pads level 7
  • Set MEP equipment level 7
  • Framing level 6
  • MEP overhead and in-wall rough level 6
  • MEP rough OH and in-wall level 5
  • Drywall level 5
  • Sheetrock level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger elevators
  • Deliver service elevators
  • Frame stair 1


Week of January 26, 2026

  • MEP install level 10
  • Install roofing level 10
  • Build switchgear level 9
  • Run conduit for switchgear from 1 to 9
  • Build exterior walls level 9
  • Rig and set AHU and plumbing equipment level 8
  • Curtainwall install 1, 8 and 9
  • Low pressure ductwork level 7
  • Epoxy pads level 7
  • Set MEP equipment level 7
  • Framing level 6
  • MEP overhead and in-wall rough level 6
  • Drywall level 5
  • Tape level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger elevators
  • Install service elevators
  • Frame stair 1
     

Week of February 2, 2026

  • MEP install level 10
  • Install roofing level 10
  • Build switchgear level 9
  • Build exterior walls level 9
  • Rig and set plumbing equipment level 8
  • Low pressure ductwork level 7
  • In-wall blocking level 7
  • Set MEP equipment level 7
  • Framing level 6
  • MEP overhead and in-wall rough level 6
  • Drywall level 5
  • Prime paint level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger elevators
  • Install service elevators
  • Frame stair 1

     


 


 

aerial view of Danoff construction site 11.2025