William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

November 2026

Week of November 16, 2026

  • Fire Alarm Programing and Testing
  • Balancing
  • Start-Up and Commissioning of Equipment
  • Install Control Wiring Level 8
  • Tel-Data / Security Level 8
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Base Level 6
  • Finish Hub and Bathroom Level 6
  • Rough Clean Level 6
  • Complete Bathrooms Level 5
  • Complete Hub Ceiling Level 5
  • Polished Concrete Level 1
  • Millwork Install Level 1
  • Ceiling Level 1
  • Loading Dock Equipment Install
  • Landscape along Elm St
  • Granite Seawall and Bench Install

Week of November 23, 2026

  • Site Closed Thursday 11/26 for Thanksgiving
  • Fire Alarm Programing and Testing
  • Balancing
  • Start-Up and Commissioning of Equipment
  • Install Control Wiring Level 8
  • Tel-Data / Security Level 8
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Finish Hub and Bathroom Level 6
  • Complete Bathrooms Level 5
  • Complete Hub Ceiling Level 5
  • Polished Concrete Level 1
  • Millwork Install Level 1
  • Casework Level 1
  • Landscape along Elm St
  • Granite Seawall and Bench Install

Week of November 30, 2026

  • Fire Alarm Programing and Testing
  • Balancing
  • Start-Up and Commissioning of Equipment
  • Install Control Wiring Level 8
  • Tel-Data / Security Level 8
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Rough Clean Level 6
  • Complete Bathrooms Level 6
  • Complete Hub Millwork Level 5 and 6
  • Millwork Install Level 1
  • Casework Level 1
  • Landscape along Elm St
  • Granite Seawall and Bench Install