William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - March 27, 2026
  • Elbow Street closed for bridge detailing

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

 March/APRIL 2026

Week of March 23, 2026

  • Roof flashing level 9 and 10
  • Buildout switchgear level 9
  • MEP equipment connections level 8
  • Install final roof level 8
  • Install flashings level 9 and 10
  • In-wall rough level 7
  • Framing level 7
  • MEP overhead rough level 6
  • Blocking, drywall, taping level 6
  • Tape and paint level 5
  • Install metal panel mezzanine level
  • Prime and paint level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • AVB and Z-Girt loading dock
  • Install site drainage structures and piping
  • Metal panel exterior soffits
     

Week of March 30, 2026
 

  • Buildout switchgear level 9
  • MEP equipment connections level 8
  • Buildout level 8 generator room
  • Install final roof level 8
  • Install flashings level 9 and 10
  • In-wall rough and blocking level 7
  • Framing level 7
  • In-wall rough level 6
  • Blocking, drywall, taping level 6
  • Tape and paint level 5
  • K-13 install level 5
  • Install metal panel mezzanine level
  • Install ceilings level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Metal panel exterior soffits
     

Week of April 6, 2026
 

  • Buildout switchgear level 9
  • MEP equipment connections level 8
  • Buildout level 8 generator room
  • Install final roof level 8
  • In-wall rough and blocking level 7
  • Framing level 7
  • Blocking, drywall, taping level 6
  • Tape and paint level 5
  • K-13 install level 5
  • Install metal panel mezzanine level
  • Install ceilings level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Install fencing at electric yard
  • Metal panel exterior soffit