Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2- October 4, 2025
  • Elbow Street closed for bridge detailing


 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

September 2025

Week of September 8, 2025

  • Deck and detail level 9 and penthouse roof
  • Pour level 8
  • Continue spray fireproofing level 1 & 6
  • Site utility install
  • Install MEP risers
  • Early wall install level 3 and 4
  • MEP install level 3 and 4
  • Masonry walls and framing at loading dock
  • Install clips at bridge
  • Pour bridge slab
  • Mobilize curtainwall

Week of September 15, 2025

  • Deck and detail penthouse roof
  • Pour level 9
  • Continue spray fireproofing level 6 and 7
  • Site utility install
  • Install MEP risers
  • Early walls and MEPs on level 4 and 5
  • Masonry walls and exterior framing at loading dock
  • Shake out and install curtainwall
  • Fireproofing at bridge
 

Week of September 22, 2025

  • Deck and detail penthouse roof
  • Pour level 9
  • Continue spray fireproofing level 7
  • Site utility install
  • Install MEP risers
  • Early walls and MEPs on level 5
  • Masonry walls and exterior framing at loading dock
  • Curtain wall install
  • Install MEPs at bridge
     
 

Danoff Steel Erection graphic