Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - March 27, 2026
- Elbow Street closed for bridge detailing

Construction Updates
Please note, scope may change based on existing conditions found in the field.
March 2026
Week of March 2, 2026
- MEP install level 10
- Install roofing level 10
- Roof flashing level 9 and 10
- Run conduit for switchgear from 1 to 9
- Build switchgear level 9
- Install grating at level 9 dunnage
- Rig and set plumbing equipment level 8
- Install flashings level 9 and 10
- Low pressure ductwork and MEP rough level 7
- Framing level 7
- MEP overhead and in-wall rough 6
- Taping and drywall level 5
- Install metal panel level 4 north
- Tape level 2
- MEP rough on level 1
- Install level 1 curtainwall
- Core board shafts
- Frame and Sheath Stair 1
- Install passenger and service Elevators
- Install granite level 1
Week of March 9, 2026
- Roof flashing level 9 and 10
- Run conduit for switchgear from 1 to 9
- Build switchgear level 9
- Install grating at level 9 dunnage
- Frame and sheath exterior walls level 9
- Rig and set plumbing equipment level 8
- Install flashings level 9 and 10
- Low pressure ductwork and MEP rough level 7
- Framing level 7
- MEP overhead and in-wall rough 6
- Drywall level 6
- Drywall, taping, painting level 5
- Install metal panel level 4 north
- Prime and paint level 2
- MEP rough on level 1
- Core board shafts
- Install passenger and service Elevators
- Install granite level 1
- Take down tower crane March 12th to 15th (5am to 7pm)
Week of March 16, 2026
- Roof flashing level 9 and 10
- Run conduit for switchgear from 1 to 9
- Install grating at level 9 dunnage
- Frame and sheath exterior walls level 9
- Rig and set plumbing equipment level 8
- Install flashings level 9 and 10
- In-wall rough and blocking level 7
- Framing level 7
- Blocking, drywall and taping level 6
- Taping and painting level 5
- Install K-13 level 5
- Install metal panel mezzanine level
- Prime and paint level 2
- MEP rough on level 1
- Core board shafts
- Install passenger and service elevatorsInstall granite level 1