Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
August 18-19, 2025
- Elbow Street closure between Ship Street and Chestnut Street
August 20, 2025
- Elm Street closure between Richmond Street and Chestnut Street 10 AM - 4 PM
Construction Updates
Please note, scope may change based on existing conditions found in the field.
July - August 2025![]()
Week of July 28, 2025
- Continue structural steel erection level 9
- Deck and detail level 6 and 7
- Pour slab on grade
- Complete underslab MEPs
- Continue spray fireproofing level 3
- Site utility install
Week of August 4, 2025
- Continue structural steel erection level 9
- Deck and detail level 7
- Pour level 6 north and south and slab on grade
- Complete underslab MEPs
- Continue spray fireproofing level 3
- Site utility install
- MEP rough-in level 2
- Early wall install mezzanine
Week of August 11, 2025
- Site closed Monday, August 11 for Victory Day
- Continue structural steel erection roof
- Install V columns for bridge on Elbow Street
- Deck and detail level 7 and 8
- Pour level 6 north and south and slab on grade
- Complete underslab MEPs
- Continue spray fireproofing level 3 and loading dock
- Site utility install