Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - October 4, 2025
- Elbow Street closed for bridge detailing
Construction Updates
Please note, scope may change based on existing conditions found in the field.
September/October 2025
Week of September 22, 2025
- Deck and detail penthouse roof
- Pour level 9
- Continue spray fireproofing levels 6, 7, 8
- Site utility install
- Install MEP risers
- Early walls and MEPs on levels 4-6
- Masonry walls and exterior framing at loading dock
- Curtain wall install
- Install roofing level 5
- Fireproofing at bridge
Week of September 29, 2025
- Pour level 9
- Continue spray fireproofing level 7 and 8
- Site utility install
- Install MEP risers
- Early walls and MEPs on level 5
- Masonry walls and exterior framing at loading dock
- Curtain wall install
- Install MEPs at bridge
- Install roofing level 5
Week of October 6, 2025
- Pour penthouse roof
- Continue spray fireproofing level 9
- Site utility install
- Install MEP risers
- Early walls and MEPs on level 6
- Masonry walls and exterior framing at loading dock
- Curtain wall install
- Install MEPs at bridge
- Install temporary roof level 8