Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
  • June 8th thru September 6th  Richmond Street northbound closed for landscaping/sidewalk install
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

August 2026
 Week of August 17, 2026
  • Power and lighting Level 9
  • Install valves and control wiring Level 8
  • Terminate electrical panels Level 8
  • Fill and flush hot water
  • Drywall and tape Level 8
  • Epoxy walls and floors Level 7
  • MEP finishes Level 7
  • Seal concrete Level 6
  • Fabric panels Level 6
  • Hub ceiling Level 5
  • Fabric panels Level 5
  • Sealed concrete Level 5
  • Hub ceiling Install Level 5
  • Fin Tube Install Level 5
  • Taping Level 1
  • Clark Door install Level 1
  • K-13start Level 1
  • Painting Level 1
  • MEP Finishes Level 1
  • Clark Door Install Level 1
  • Install passenger and jump elevator
  • Install light pole bases
  • Form and pour site sidewalks
  • Cox relocation of conduit Second Shift
  • Landscaping along Richmond Street
Week of August 24, 2026
  • Power and lighting Level 9
  • Install valves and control wiring Level 8
  • Terminate Electrical Panels Level 8
  • Fill and flush hot water system
  • Epoxy walls and floors Level 7
  • MEP finishes Level 7
  • Seal concrete Level 6
  • Fabric panels Level 6
  • Hub ceiling Level 5
  • Sealed concrete Level 5
  • Hub ceiling install Level 5
  • Fin Tube install Level 5
  • Clark Door install Level 1
  • Paint Level 1
  • Ceiling install Level 1
  • MEP Finishes Level 1
  • Install passenger and jump elevator
  • Form and pour site sidewalks 
  • Cox relocation of conduit Second Shift
  • Landscaping along Richmond Street
Week of August 31, 2026
  • Power and lighting Level 9
  • Install valves and control wiring Level 8
  • Epoxy walls and floors Level 7
  • MEP finishes Level 7
  • Seal concrete Level 6
  • Fabric panels Level 6
  • Hub ceiling Level 5
  • Sealed concrete Level 5
  • Hub ceiling install Level 5
  • Fin Tube install Level 5
  • Ceiling install Level 5
  • Carpet install Level 5
  • Ceiling install Level 1
  • Painting Level 1
  • MEP finishes Level 1
  • Polished concrete Level 5
  • Install passenger and jump elevator
  • Form and pour site sidewalks
  • Cox relocation of conduit Second Shift
  • Landscaping along Richmond Street