Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
June 2, 2025 to July 11, 2025
- Richmond Street southbound and northbound lane closure.
- Richmond Street northbound sidewalk partially closed during business hours, Warren Alpert Building to remain accessible.
Construction Updates
Please note, scope may change based on existing conditions found in the field.
June - July 2025
Week of June 23, 2025
- Continue structural steel erection level 7
- Deck and detail level 5
- Pour level 2 south and slab on grade north
- Continue underground electrical slab on grade
- Continue underground plumbing at slab on grade
- Continue mitigated loop on Richmond Street (street closure)
Week of June 30, 2025
- Site closed July 4, 2025 in observance of Independence Day
- Continue structural steel erection level 7
- Deck and detail levels 5-6
- Pour level 3 north and slab on grade
- Continue underground electrical at slab on grade
- Continue underground plumbing at slab on grade
- Continue mitigated loop on Richmond Street (street closure)
Week of July 7, 2025
- Continue structural steel erection level 8
- Deck and detail levels 5-6
- Pour level 3 south and slab on grade
- Continue underground electrical at slab on grade
- Continue underground plumbing at slab on grade
- Continue mitigated loop on Richmond Street (street closure)
- RI Energy work on Elbow-Chestnut Street (street closure)