Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
- June 8th thru September 6th Richmond Street northbound closed for landscaping/sidewalk install

Construction Updates
Please note, scope may change based on existing conditions found in the field.
August 2026
Week of August 3, 2026
- Fire Alarm Level 9
- Power and Lighting Level 9
- Install Valves and Control Wiring Level 8
- Terminate Electrical Panels Level 8
- Drywall and Tape Hard Ceilings Level 7
- Epoxy Walls and Floors Level 7
- Overhead MEP Rough Level 7
- Lab Casework Install Level 6
- Install Aluminum Frames Level 6
- Polished Concrete Level 6
- Install Aluminum Frames and Glass Partitions Level 5
- Hoist Infill Level 5
- Install Sealed Concrete Level 5
- Fabric Panels Level 5
- In-Wall Rough Levels 2-4
- Drywall and Taping Level 1
- In-Wall Rough Level 1
- AV Rack Install Level 1
- Install Passenger and Jump Elevator
- Install Light Pole Bases
- Form and Pour Sidewalks on Chestnut and Elbow St
- Cox Relocation of Conduit Second Shift
- Landscaping Along Richmond St
Week of August 10, 2026
- Site Closed Monday 8/10 for Victory Day
- Power and Lighting Level 9
- Install Valves and Control Wiring Level 8
- Terminate Electrical Panels Level 8
- Fill and Flush Hot WAter
- Epoxy Walls and Floors Level 7
- Overhead MEP Rough Level 7
- Lab Casework Install Level 6
- Install Aluminum Frames Level 6
- Fabric and Glass Boards Level 6
- Fabric Panels Level 6
- Polished Concrete Level 6
- Install Aluminum Frames Level 5
- Fabric Panels Level 5
- Sealed Concrete Level 5
- In-Wall Rough Levels 2-4
- Taping Level 1
- AV Rack Install Level 1
- K-13 Start Level 1
- Install Passenger and Jump Elevator
- Install Light Pole Bases
- Form and Pour Sidewalks on Chestnut and Elbow St
- Cox Relocation of Conduit Second Shift
- Landscaping Along Richmond St
Week of August 17, 2026
- Power and Lighting Level 9
- Install Valves and Control Wiring Level 8
- Terminate Electrical Panels Level 8
- Epoxy Walls and Floors Level 7
- MEP Finishes Level 7
- Seal Concrete Level 6
- Fabric Panels Level 6
- Hub Ceiling Level 5
- Fabric Panels Level 5
- Sealed Concrete Level 5
- Taping Level 1
- Clark Door Install Level 1
- K-13 Start Level 1
- Install Passenger and Jump Elevator
- Install Light Pole Bases
- Form and Pour Sidewalks on Chestnut and Elbow St
- Cox Relocation of Conduit Second Shift
- Landscaping Along Richmond St