Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - January 17, 2026
- Elbow Street closed for bridge detailing

Construction Updates
Please note, scope may change based on existing conditions found in the field.
January 2026
Week of January 12, 2026
- MEP install level 10
- Set EAHU on level 9
- Build switchgear level 9
- Curtainwall install levels 1 and 8
- Low pressure ductwork level 8
- Epoxy pads level 8
- Set MEP equipment level 7
- Framing level 6
- MEP rough OH and in-wall level 5
- Level 5 in-wall inspections
- MEP rough on level 1
- Core board shafts
- Install passenger elevators
- Frame stair 1
- Sheetrock level 2
Week of January 19, 2026
- MEP install level 10
- Rig and set AHU and plumbing equipment level 8
- Build switchgear level 9
- Run conduit for switchgear from 1 to 9
- Curtainwall install 1, 8 and 9
- Low pressure ductwork level 7
- Epoxy pads level 7
- Set MEP equipment level 7
- Framing level 6
- MEP overhead and in-wall rough level 6
- MEP rough OH and in-wall level 5
- Drywall level 5
- Sheetrock level 2
- MEP rough on level 1
- Core board shafts
- Install passenger elevators
- Deliver service elevators
- Frame stair 1
Week of January 26, 2026
- MEP install level 10
- Install roofing level 10
- Build switchgear level 9
- Run conduit for switchgear from 1 to 9
- Build exterior walls level 9
- Rig and set AHU and plumbing equipment level 8
- Curtainwall install 1, 8 and 9
- Low pressure ductwork level 7
- Epoxy pads level 7
- Set MEP equipment level 7
- Framing level 6
- MEP overhead and in-wall rough level 6
- MEP rough OH and in-wall level 5
- Drywall level 5
- Tape level 2
- MEP rough on level 1
- Core board shafts
- Install passenger elevators
- Deliver service elevators
- Frame stair 1
