William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - January 17, 2026
  • Elbow Street closed for bridge detailing


 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

December 2025 / January 2026

Week of December 22, 2025

  • Site closed Thursday December 25, 2025 for Christmas
  • Install roofing level 9
  • MEP mains level 8
  • Set MEP equipment level 1 and 8
  • Curtainwall install 1,7 and 8 
  • MEP rough level 5
  • Ductwork install level 6
  • Exterior masonry on level 1
  • Framing level 5 north
  • Level 5 overhead and in-wall MEP rough
  • Install tarps on level 8 and 9 
  • MEP rough on level 1
  • Pour pads on level 1
  • Install passenger elevators
  • Deliver service elevators
  • In-wall rough level 2
  • Frame stair 1


Week of December 29, 2025

  • Site closed Thursday, January 1, 2026 for New Years Day
  • Install roofing level 9
  • Form and pour AHU pads
  • Set MEP equipment level 1 and 8
  • Curtainwall install 1 and 8
  • MEP rough OH and in-wall level 5
  • Ductwork install level 6
  • Framing level 6
  • Exterior masonry on level 1
  • Framing level 5 north
  • Level 5 overhead MEP rough
  • MEP rough on level 1
  • Pour pads on level 1
  • Install passenger elevators
  • Frame stair 1
  • Install drywall level 2


Week of January 5, 2026

  • Install roofing level 9
  • Form and pour AHU pads
  • Set MEP equipment level 1 and 8
  • Curtainwall install 1, 8 and 9
  • MEP rough OH and in-wall level 5
  • Ductwork install level 6
  • Framing level 6
  • Exterior masonry on level 1
  • Framing level 5 north, in-wall inspections and blocking
  • Level 5 overhead MEP rough
  • MEP rough on level 1
  • Pour pads on level 1
  • Install passenger elevators
  • Frame stair 1
  • Install drywall level 2

     


 


 

aerial view of Danoff construction site 11.2025