Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - March 27, 2026
- Elbow Street closed for bridge detailing
March 12 thru March 20
•Elbow and Chestnut Street closed 6 AM thru 7 PM for tower crane removal

Construction Updates
Please note, scope may change based on existing conditions found in the field.
March 2026
Week of March 16, 2026
- Take down tower crane March 17th to 20th (6am to 7pm)
- Roof flashing level 9 and 10
- Run conduit for switchgear from 1 to 9
- Tape and paint walls level 9
- MEP equipment connections level 8
- Install final roof level 8
- Install flashings level 9 and 10
- In-wall rough level 7
- Framing level 7
- MEP overhead rough level 6
- Blocking and drywall level 6
- Drywall and taping level 5
- Install metal panel mezzanine level
- Prime and paint level 2
- MEP rough on level 1
- Install passenger and service elevators
- Install granite level 1
- Sheath exterior soffits
Week of March 23, 2026
- Roof flashing level 9 and 10
- Buildout switchgear level 9
- MEP equipment connections level 8
- Install final roof level 8
- Install flashings level 9 and 10
- In-wall rough level 7
- Framing level 7
- MEP overhead rough level 6
- Blocking, drywall, taping level 6
- Tape and paint level 5
- Install metal panel mezzanine level
- Prime and paint level 2
- MEP rough on level 1
- Install passenger and service elevators
- Install granite level 1
- Install site drainage structures and piping
- Metal panel exterior soffits
Week of March 30
- Buildout switchgear level 9
- MEP equipment connections level 8
- Install final roof level 8
- Install flashings level 9 and 10
- In-wall rough and blocking level 7
- Framing level 7
- Blocking, drywall, taping level 6
- Tape and paint level 5
- K-13 install level 5
- Install metal panel mezzanine level
- Install ceilings level 2
- MEP rough on level 1
- Install passenger and service elevators
- Install granite level 1
- Install site drainage structures and piping
- Install light pole bases
- Install fencing at electric yard
- Metal panel exterior soffits