Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

October 2026

Week of October 12, 2026

  • Site Closed Monday 10/12
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Carpet Install Level 6
  • Glass Wall Install Level 6
  • Final Paint Level 6
  • Rough Clean Level 5
  • Polished Concrete Level 5
  • Finishes by Hoist Infill Level 5
  • Glass Wall Install Level 5
  • MEP Ceiling Finishes Level 2
  • Polished Concrete Level 1
  • Flooring Level 1
  • Paint Level 1
  • Form and Pour Site Sidewalks
  • Landscaping Along Richmond St
  • Granite Seawall and Bench Install

Week of October 19, 2026

  • Insulate Level 9
  • Install Valves and Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Carpet Install Level 6
  • Glass Wall Install Level 6
  • Final Paint Level 6
  • Rough Clean Level 5
  • Finishes by Hoist Infill Level 5
  • White Out Ceilings Level 2
  • Final Paint Level 2
  • Polished Concrete Level 1
  • Flooring Level 1
  • Paint Level 1
  • Aluminum Frame Install Level 1
  • Form and Pour Site Sidewalks
  • Landscaping Along Richmond St
  • Granite Seawall and Bench Install

Week of October 26, 2026

  • Insulate Level 9
  • Install Valves and Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Base Install Level 6
  • Finishes by Hoist Infill Level 5
  • Carpet Level 2
  • Polished Concrete Level 1
  • Flooring Level 1
  • Paint Level 1
  • Aluminum Frame Install Level 1
  • Form and Pour Site Sidewalks
  • Landscaping Along Richmond St
  • Granite Seawall and Bench Install