Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
- June 8th thru September 6th Richmond Street northbound closed for landscaping/sidewalk install

Construction Updates
Please note, scope may change based on existing conditions found in the field.
August 2026
Week of August 17, 2026
- Power and lighting Level 9
- Install valves and control wiring Level 8
- Terminate electrical panels Level 8
- Fill and flush hot water
- Drywall and tape Level 8
- Epoxy walls and floors Level 7
- MEP finishes Level 7
- Seal concrete Level 6
- Fabric panels Level 6
- Hub ceiling Level 5
- Fabric panels Level 5
- Sealed concrete Level 5
- Hub ceiling Install Level 5
- Fin Tube Install Level 5
- Taping Level 1
- Clark Door install Level 1
- K-13start Level 1
- Painting Level 1
- MEP Finishes Level 1
- Clark Door Install Level 1
- Install passenger and jump elevator
- Install light pole bases
- Form and pour site sidewalks
- Cox relocation of conduit Second Shift
- Landscaping along Richmond Street
Week of August 24, 2026
- Power and lighting Level 9
- Install valves and control wiring Level 8
- Terminate Electrical Panels Level 8
- Fill and flush hot water system
- Epoxy walls and floors Level 7
- MEP finishes Level 7
- Seal concrete Level 6
- Fabric panels Level 6
- Hub ceiling Level 5
- Sealed concrete Level 5
- Hub ceiling install Level 5
- Fin Tube install Level 5
- Clark Door install Level 1
- Paint Level 1
- Ceiling install Level 1
- MEP Finishes Level 1
- Install passenger and jump elevator
- Form and pour site sidewalks
- Cox relocation of conduit Second Shift
- Landscaping along Richmond Street
Week of August 31, 2026
- Power and lighting Level 9
- Install valves and control wiring Level 8
- Epoxy walls and floors Level 7
- MEP finishes Level 7
- Seal concrete Level 6
- Fabric panels Level 6
- Hub ceiling Level 5
- Sealed concrete Level 5
- Hub ceiling install Level 5
- Fin Tube install Level 5
- Ceiling install Level 5
- Carpet install Level 5
- Ceiling install Level 1
- Painting Level 1
- MEP finishes Level 1
- Polished concrete Level 5
- Install passenger and jump elevator
- Form and pour site sidewalks
- Cox relocation of conduit Second Shift
- Landscaping along Richmond Street