Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - May 30, 2026
- Elbow Street closed for bridge detailing

Construction Updates
Please note, scope may change based on existing conditions found in the field.
APRIL/MAY 2026
Week of April 20, 2026
- Buildout switchgear level 9
- Level 8 roof
- In-wall rough and blocking level 7
- Overhead rough/insulation level 7
- In-wall inspection level 7
- MEP overhead rough level 6
- Taping level 6
- Bathroom tile level 5
- Paint level 5
- Install ceilings and chilled beams level 5
- MEP ceiling install level 2
- Bathroom fixture install level 2
- MEP rough on level 1
- Framing level 1
- Install passenger and service elevators
- Install granite level 1
- Install site drainage structures and piping
- Install fencing at electric yard
- Start landscaping on western side of site
Week of April 27, 2026
- Buildout switchgear level 9
- In-wall rough and blocking level 7
- Sheetrock level 7
- Overhead rough/insulation level 7
- In-wall inspection level 7
- MEP overhead rough level 6
- Taping and painting level 6
- K-13 install level 5
- Bathroom tile level 5
- Paint level 5
- Install ceilings and chilled beams level 5
- MEP rough on Level 1
- Framing level 1
- In-wall rough level 1
- Install passenger and service elevators
- Install granite level 1
- Install site drainage structures and piping
- Install fencing at electric yard
Week of May 4, 2026
- Buildout switchgear level 9
- In-wall rough and blocking level 7
- Sheetrock level 7
- Overhead rough/insulation level 7
- In-wall inspection level 7
- Paint level 6
- K-13 level 6
- Paint level 5
- Install ceilings and chilled beams level 5
- Moisture mitigation level 5
- MEP rough on level 1
- Framing level 1
- In-wall rough level 1
- Install passenger and service elevators
- Install granite level 1
- Install site drainage structures and piping
- Power live at RI switchyard