William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - May 30, 2026
  • Elbow Street closed for bridge detailing

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

MAY 2026

Week of May 18, 2026

  • Roofing punchlist and flashing
  • Buildout switchgear Level 9
  • Install ductwork Level 9
  • Install panels and control wiring Level 8
  • Install valves Level 8
  • Final MEP connections Level 8
  • In-wall rough and blocking Level 7
  • Sheetrock Level 7
  • Overhead rough/insulation Level 7
  • K-13 Level 6
  • Painting Level 6
  • Chilled beam install and insulation Level 6
  • Moisture mitigation and flooring Level 5
  • Install ceilings level 5
  • MEP overhead rough on Level 1
  • Framing and in-wall rough Level 1
  • Install passenger and service elevators
  • Install granite Level 1
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow St
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building
     
Week of May 25, 2026
  • Site closed Monday May 25th
  • Buildout switchgear Level 9
  • Install ductwork Level 9
  • Install panels and control wiring Level 8
  • Install valves Level 8
  • Final MEP connections Level 8
  • In-wall rough and blocking Level 7
  • Sheetrock Level 7
  • Overhead rough/insulation Level 7
  • K-13 Level 6
  • Painting Level 6
  • Chilled beam install and insulation Level 6
  • Moisture mitigation and bathroom tile Level 6
  • Moisture mitigation and flooring Level 5
  • MEP overhead rough on Level 1
  • Framing and in-wall rough Level 1
  • Install passenger and service elevators
  • Install granite Level 1
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow St
  • Form and pour walls at Gate C
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building

Week of June 1, 2026

  • Test wire and breakers Level 9
  • Install ductwork Level 9
  • Install panels and control wiring Level 8
  • Install valves Level 8
  • Final MEP connections Level 8
  • In-wall rough and blocking Level 7
  • Sheetrock Level 7
  • Overhead rough/insulation Level 7
  • Chilled beam install and insulation Level 6
  • Moisture mitigation, flooring, and bathroom tile Level 6
  • Install flooring Level 5
  • Lab casework Level 5
  • MEP rough on Level 1
  • Framing and in-wall rough Level 1
  • Install passenger and service elevators
  • Install granite Level 1
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow St
  • Form and pour walls at Gate C
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building