Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - December 13, 2025
- Elbow Street closed for bridge detailing

Construction Updates
Please note, scope may change based on existing conditions found in the field.
November/December 2025
Week of November 24, 2025
- Site Closed Thursday, 11/27 for Thanksgiving
- Install roofing level 9
- Install tarps on level 8 and 9
- Ductwork and MEP mains level 8
- Curtainwall install level 5 and 6
- Low pressure ductwork on level 5
- Exterior masonry on level 1
- Curtainwall starter sill level 1
- Install roof at bridge
- Frame level 2 and in-wall rough
- MEP rough on level 1
- Rig and set penthouse and level 1 equipment
- Install passenger elevators
- Frame and board stair 3
- Temporary heat live
Week of December 1, 2025
- Install roofing level 9
- Install tarps on level 8 and 9
- Ductwork and MEP mains level 8
- Curtainwall install level 1 and 6
- In-wall rough level 2
- Exterior masonry on level 1
- Install MEPs at bridge
- MEP rough on level 1
- Rig and set level 1 and PH equipment
- Install passenger elevators
- Frame and board stair 3
Week of December 8, 2025
- Install roofing level 9
- Ductwork and MEP mains level 8
- Curtainwall install 7 and 1
- Exterior masonry on level 1
- Framing level 5 north
- Level 5 overhead MEP rough
- Install tarps on level 8 and 9
- MEP rough on level 1
- Install passenger elevators
- In-wall inspections level 2
- Sheetrock level 2
