William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

November 2026

Week of November 2, 2026

  • Test and Insulate Equipment Level 9
  • Install Control Wiring Level 8
  • MEP Connection Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Carpet and Paint Level 6
  • Punchlist Level 5
  • Complete Bathrooms Level 5
  • Complete Hub Level 5
  • Polished Concrete Level 1
  • Casework Install Level 1
  • Millwork Install Level 1
  • Paint Level 1
  • Loading Dock Equipment Install
  • Form and Pour Site Sidewalks
  • Granite Seawall and Bench Install

Week of November 9, 2026

  • Site Closed Wednesday 11/11 for Veteran’s Day
  • Test and Insulate Equipment Level 9
  • Install Control Wiring Level 8
  • MEP Connection Level 8
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Base Level 6
  • Rough Clean Level 6
  • Punchlist Level 5
  • Complete Bathrooms Level 5
  • Complete Hub Level 5
  • Polished Concrete Level 1
  • Casework Install Level 1
  • Millwork Install Level 1
  • Paint Level 1
  • Loading Dock Equipment Install
  • Form and Pour Site Sidewalks
  • Granite Seawall and Bench Install
     
Week of November 16, 2026
  • Test and Insulate Equipment Level 9
  • -nstall Control Wiring Level 8
  • MEP Connection Level 8
  • Doors and Frame Install Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Base Level 6
  • Rough Clean Level 6
  • Punchlist Level 5
  • Complete Bathrooms Level 5
  • Complete Hub Level 5
  • Polished Concrete Level 1
  • Casework Install Level 1
  • Millwork Install Level 1
  • Paint Level 1
  • Loading Dock Equipment Install
  • Form and Pour Site Sidewalks
  • Granite Seawall and Bench Install