Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - May 30, 2026
- Elbow Street closed for bridge detailing

Construction Updates
Please note, scope may change based on existing conditions found in the field.
MAY 2026
Week of May 18, 2026
- Roofing punchlist and flashing
- Buildout switchgear Level 9
- Install ductwork Level 9
- Install panels and control wiring Level 8
- Install valves Level 8
- Final MEP connections Level 8
- In-wall rough and blocking Level 7
- Sheetrock Level 7
- Overhead rough/insulation Level 7
- K-13 Level 6
- Painting Level 6
- Chilled beam install and insulation Level 6
- Moisture mitigation and flooring Level 5
- Install ceilings level 5
- MEP overhead rough on Level 1
- Framing and in-wall rough Level 1
- Install passenger and service elevators
- Install granite Level 1
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut and Elbow St
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building
Week of May 25, 2026
- Site closed Monday May 25th
- Buildout switchgear Level 9
- Install ductwork Level 9
- Install panels and control wiring Level 8
- Install valves Level 8
- Final MEP connections Level 8
- In-wall rough and blocking Level 7
- Sheetrock Level 7
- Overhead rough/insulation Level 7
- K-13 Level 6
- Painting Level 6
- Chilled beam install and insulation Level 6
- Moisture mitigation and bathroom tile Level 6
- Moisture mitigation and flooring Level 5
- MEP overhead rough on Level 1
- Framing and in-wall rough Level 1
- Install passenger and service elevators
- Install granite Level 1
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut and Elbow St
- Form and pour walls at Gate C
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building
Week of June 1, 2026
- Test wire and breakers Level 9
- Install ductwork Level 9
- Install panels and control wiring Level 8
- Install valves Level 8
- Final MEP connections Level 8
- In-wall rough and blocking Level 7
- Sheetrock Level 7
- Overhead rough/insulation Level 7
- Chilled beam install and insulation Level 6
- Moisture mitigation, flooring, and bathroom tile Level 6
- Install flooring Level 5
- Lab casework Level 5
- MEP rough on Level 1
- Framing and in-wall rough Level 1
- Install passenger and service elevators
- Install granite Level 1
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut and Elbow St
- Form and pour walls at Gate C
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building