Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - November 1, 2025
- Elbow Street closed for bridge detailing

 
Construction Updates
Please note, scope may change based on existing conditions found in the field.
October/November 2025
Week of October 27, 2025
- Spray fireproofing level 9
- Form and pour penthouse mechanical pads/curbs
- Early walls and MEPs on level 7
- Set MEP mains level 8
- Curtain wall install level 4
- Install parapet walls on levels 8-10
- Install temporary roofing level 8 and cooling tower well
- Install roofing on bridge
- Early walls level 1
- Exterior framing, sheathing, AVB on level 1
- Install temporary heat piping and duct
- Install tarps and temporary doors levels 1, 8, and 9
- Load elevator material
Week of November 3, 2025
- Spray fireproofing penthouse
- Form and pour penthouse mechanical pads/curbs
- Early walls and MEPs on level 7
- Set MEP mains level 8
- Curtain wall install levels 4 and 5
- Install parapet walls on levels 8-10
- Install temporary roofing level 10
- Install roofing level 9
- Early walls and MEPs level 1 and 7
- Exterior masonry on level 1
- Install tarps and temporary doors Levels 1, 8, and 9
- Install temporary heaters
- Load elevator material
Week of November 10, 2025
- Site closed Tuesday 11/11 for Veteran’s Day
- Form and pour level 9 pads
- Install roofing level 9
- Early MEPs and walls level 7
- Ductwork and MEP mains level 8
- Curtainwall install level 5
- Exterior masonry on level 1
- Install tarps on level 8 and 9 
 
