Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
- May 26th thru June 30th Elbow Street for sidewalk installation
- June 8th thru August 31st Richmond Street northbound closed for landscaping/sidewalk install

Construction Updates
Please note, scope may change based on existing conditions found in the field.
June 2026
Week of June 15, 2026
- Site closed Friday June 19th for Juneteenth
- Power and lighting Level 9
- Fire alarm Level 9
- Install panels and control wiring Level 8
- Fill and flush equipment Level 8
- Taping Level 7
- Sheetrock Level 7
- Overhead rough/insulation Level 7
- Install flooring Level 6
- Bathroom tile Level 6
- Painting level 6
- Install flooring Level 5
- Lab casework Level 5
- MEP rough on Level 1
- Drywall Level 1
- Install passenger and service elevators
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut and Elbow Streets
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building
Week of June 22, 2026
- Power and lighting Level 9
- Fire alarm Level 9
- Install panels and control wiring Level 8
- Equipment start-up Level 8
- Fill and flush equipment Level 8
- Taping Level 7
- Sheetrock Level 7
- Overhead rough/insulation Level 7
- Install flooring Level 6
- Bathroom tile Level 6
- Painting Level 6
- Lab casework Level 5
- Drywall and taping Level 1
- Install passenger and service elevators
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut and Elbow Streets
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building
- Landscaping along Richmond Street
Week of June 29, 2026
- Power and lighting Level 9
- Fire alarm Level 9
- Install panels and control wiring Level 8
- Equipment start-up Level 8
- Taping Level 7
- Sheetrock Level 7
- Overhead rough/insulation Level 7
- Install flooring Level 6
- Lab casework Level 6
- Lab casework Level 5
- Drywall and taping Level 1
- Service elevator live
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut and Elbow Streets
- Cox relocation of conduit
- Bring landscape to subgrade on west side of building
- Landscaping along Richmond Street