William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - December 13, 2025
  • Elbow Street closed for bridge detailing


 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

November 2025


Week of November 10, 2025

  • Site closed Tuesday 11/11 for Veteran’s Day
  • Form and pour level 9 and penthouse pads
  • Form and pour generator isolation slab and Café slab
  • Early MEP’s and walls level 7
  • Install temporary roofing cooling tower well and level 10
  • Install expansion joint at bridge
  • Ductwork and MEP mains level 8
  • Curtainwall install level 5
  • Exterior masonry on level 1
  • Load elevator material
  • Final connections for temp. heaters
     

Week of November 17, 2025

  • Install roofing level 9
  • Ductwork and MEP mains level 8
  • Curtainwall install level 5 and 6
  • Install curtainwall starter sill level 1
  • Install roofing at bridge
  • Exterior masonry on level 1
  • Install tarps on levels 8 and 9
  • Temporary heaters live
  • MEP rough on level 1
  • Rig and set penthouse equipment
  • Load and install elevators

Week of November 24, 2025

  • Site closed Thursday 11/27 for Thanksgiving       
  • Install roofing level 9
  • Ductwork and MEP mains level 8
  • Curtainwall install level 6 and 7
  • Exterior masonry on level 1
  • Install MEPs at bridge
  • Install tarps on level 8 and 9
  • MEP rough on level 1
  • Rig and set penthouse equipment
  • Rig and set RAHU to mezzanine level
  • Install passenger elevators
     




 

 

Danoff Steel Erection graphic