Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
June 2, 2025 to July 4, 2025
- Richmond Street southbound and northbound lane closure. Northbound to be plated and reopened daily by 3:30 PM.
- Richmond St. northbound sidewalk partially closed during business hours, Warren Alpert Building to remain accessible.
Construction Updates
Please note, scope may change based on existing conditions found in the field.
June 2025
Week of June 2, 2025
- Continue structural steel erection level 5
- Deck and detail levels 4-5
- Pour mezzanine slab and stair 2
- Continue underground electrical at slab on grade
- Continue underground plumbing at slab on grade
- Install MEP sleeves and rebar on level 2 north
- Continue reno of 70 Ship Street
- Mobilize for mitigated loop on Richmond Street (street closure)
Week of June 9, 2025
- Continue structural steel erection level 6
- Deck and detail levels 4-5
- Pour level 2 north slab
- Continue underground electricalat slab on grade
- Continue underground plumbing at slab on grade
- Install MEP sleeves and rebar on level 2 north
- Continue reno of 70 Ship Street
- Continue mitigated loop on Richmond Street (street closure)
Week of June 16, 2025
- Continue structural steel erection level 6
- Deck and detail level 5
- Continue underground electrical at slab on grade
- Continue underground plumbing at slab on grade
- Pour slab on grade north
- Continue reno of 70 Ship Street
- Continue mitigated loop on Richmond Street (street closure)