Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - December 13, 2025
- Elbow Street closed for bridge detailing

Construction Updates
Please note, scope may change based on existing conditions found in the field.
November 2025
Week of November 10, 2025
- Site closed Tuesday 11/11 for Veteran’s Day
- Form and pour level 9 and penthouse pads
- Form and pour generator isolation slab and Café slab
- Early MEP’s and walls level 7
- Install temporary roofing cooling tower well and level 10
- Install expansion joint at bridge
- Ductwork and MEP mains level 8
- Curtainwall install level 5
- Exterior masonry on level 1
- Load elevator material
- Final connections for temp. heaters
Week of November 17, 2025
- Install roofing level 9
- Ductwork and MEP mains level 8
- Curtainwall install level 5 and 6
- Install curtainwall starter sill level 1
- Install roofing at bridge
- Exterior masonry on level 1
- Install tarps on levels 8 and 9
- Temporary heaters live
- MEP rough on level 1
- Rig and set penthouse equipment
- Load and install elevators
Week of November 24, 2025
- Site closed Thursday 11/27 for Thanksgiving
- Install roofing level 9
- Ductwork and MEP mains level 8
- Curtainwall install level 6 and 7
- Exterior masonry on level 1
- Install MEPs at bridge
- Install tarps on level 8 and 9
- MEP rough on level 1
- Rig and set penthouse equipment
- Rig and set RAHU to mezzanine level
- Install passenger elevators
