Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
  • June 8th thru September 6th  Richmond Street northbound closed for landscaping/sidewalk install
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

September  2026
Week of September 7, 2026
  • Site Closed Monday 9/7/26 for Labor Day
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Fabric Panels Level 6
  • Lights Level 6
  • Hub Ceiling Install Level 5
  • Fin Tube Install Level 5
  • Ceiling Install Level 5
  • Carpet Install Level 5
  • Glass Partitions Level 5
  • Ceiling Install Level 1
  • Painting Level 1
  • MEP Finishes Level 1
  • Clark Door Install Level 1
  • Polished Concrete Level 5
  • Install Passenger and Jump Elevator
  • Form and Pour Site Sidewalks
  • Landscaping Along Richmond Street
  • Granite Seawall and Bench Install
Week of September 14, 2026
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Fabric Panels Level 6
  • Lights Level 6
  • Hub Ceiling Level 5
  • Sealed Concrete Level 5
  • Hub Ceiling Install Level 5
  • Fin Tube Install Level 5
  • Carpet Install Level 5
  • Ceiling Install Level 1
  • Painting Level 1
  • MEP Finishes Level 1
  • Clark Door Install Level 1
  • Polished Concrete Level 1
  • Install Passenger and Jump Elevator
  • Form and Pour Site Sidewalks
  • •Landscaping Along Richmond Street
  • •Granite Seawall and Bench Install
Week of September 21, 2026
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • Epoxy Walls and Floors Level 7
  • Doors and Frame Level 7
  • Casework Install Level 7
  • MEP Finishes Level 7
  • Ceiling White Out Level 6
  • Carpet Level 6
  • Lights Level 6
  • Rough Clean Level 5
  • Base Install Level 5
  • Ceiling Install Level 1
  • Painting Level 1
  • MEP Finishes Level 1
  • Clark Door Install Level 1
  • Polished Concrete Level 5
  • Granite Seawall and Bench Install