Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - November 1, 2025
  • Elbow Street closed for bridge detailing


 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

October/November 2025

Week of October 27, 2025

  • Spray fireproofing level 9
  • Form and pour penthouse mechanical pads/curbs
  • Early walls and MEPs on level 7
  • Set MEP mains level 8
  • Curtain wall install level 4
  • Install parapet walls on levels 8-10
  • Install temporary roofing level 8 and cooling tower well
  • Install roofing on bridge
  • Early walls level 1
  • Exterior framing, sheathing, AVB on level 1
  • Install temporary heat piping and duct
  • Install tarps and temporary doors levels 1, 8, and 9
  • Load elevator material

Week of November 3, 2025

  • Spray fireproofing penthouse
  • Form and pour penthouse mechanical pads/curbs
  • Early walls and MEPs on level 7
  • Set MEP mains level 8
  • Curtain wall install levels 4 and 5
  • Install parapet walls on levels 8-10
  • Install temporary roofing level 10
  • Install roofing level 9
  • Early walls and MEPs level 1 and 7
  • Exterior masonry on level 1
  • Install tarps and temporary doors Levels 1, 8, and 9
  • Install temporary heaters
  • Load elevator material


Week of November 10, 2025

  • Site closed Tuesday 11/11 for Veteran’s Day
  • Form and pour level 9 pads
  • Install roofing level 9
  • Early MEPs and walls level 7
  • Ductwork and MEP mains level 8
  • Curtainwall install level 5
  • Exterior masonry on level 1
  • Install tarps on level 8 and 9 


     
 

Danoff Steel Erection graphic