William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
    • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline

 

 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

January/February 2025

Week of January 27, 2025

  • Continue concrete foundations
  • Continue backfill of completed foundations
  • Continue waterproofing of foundations
  • Continue north core form and placement
  • Continue south core form and placement
  • Start underground electrical ductbank
  • Start underground plumbing

Week of February 3, 2025

  • Continue concrete foundations
  • Continue backfill of completed foundations
  • Continue waterproofing of foundations
  • Continue north core form and placement
  • Continue south core form and placement
  • Continue underground electrical ductbank
  • Continue underground plumbing
Week of February 10, 2025
  • Continue concrete foundations
  • Continue backfill of completed foundations
  • Continue waterproofing of foundations
  • Continue north core form and placement
  • Continue south core form and placement
  • Continue underground electrical ductbank
  • Continue underground plumbing
  • Install drain line along Richmond Street
 

Sitework map