William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - May 30, 2026
  • Elbow Street closed for bridge detailing

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

APRIL 2026

Week of April 6, 2026

  • Buildout switchgear level 9
  • MEP equipment connections level 8
  • Buildout level 8 generator room
  • Install final roof level 8
  • In-wall rough and blocking level 7
  • Framing level 7
  • Overhead and in-wall MEP rough level 6
  • Blocking, drywall, taping level 6
  • Tape and paint level 5
  • K-13 install level 5
  • Install ceilings level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Metal panel exterior soffit


Week of April 13, 2026

  • Buildout switchgear level 9
  • MEP equipment connections level 8
  • Buildout level 8 generator room
  • In-wall rough and blocking level 7
  • Overhead rough level 7
  • Drywall and taping level 7
  • Taping and painting level 6
  • Tape and paint level 5
  • K-13 install level 5
  • Install ceilings level 5
  • Install ceilings level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Install fencing at electric yard
  • Metal panel exterior soffit


Week of April 20, 2026

  • Buildout switchgear level 9
  • In-wall rough and blocking level 7
  • Overhead rough level 7
  • Drywall and taping level 7
  • Painting level 6
  • K-13 install level 6
  • Install ceilings level 5
  • Install K-13 level 2
  • MEP rough on level 1
  • Framing level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Install fencing at electric yard
  • Start landscaping on western side of site