Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
- June 8th thru September 6th Richmond Street northbound closed for landscaping/sidewalk install

Construction Updates
Please note, scope may change based on existing conditions found in the field.
September 2026
Week of September 7, 2026
- Site Closed Monday 9/7/26 for Labor Day
- Power and Lighting Level 9
- Install Valves and Control Wiring Level 8
- Epoxy Walls and Floors Level 7
- Doors and Frame Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Fabric Panels Level 6
- Lights Level 6
- Hub Ceiling Install Level 5
- Fin Tube Install Level 5
- Ceiling Install Level 5
- Carpet Install Level 5
- Glass Partitions Level 5
- Ceiling Install Level 1
- Painting Level 1
- MEP Finishes Level 1
- Clark Door Install Level 1
- Polished Concrete Level 5
- Install Passenger and Jump Elevator
- Form and Pour Site Sidewalks
- Landscaping Along Richmond Street
- Granite Seawall and Bench Install
Week of September 14, 2026
- Power and Lighting Level 9
- Install Valves and Control Wiring Level 8
- Epoxy Walls and Floors Level 7
- Doors and Frame Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Fabric Panels Level 6
- Lights Level 6
- Hub Ceiling Level 5
- Sealed Concrete Level 5
- Hub Ceiling Install Level 5
- Fin Tube Install Level 5
- Carpet Install Level 5
- Ceiling Install Level 1
- Painting Level 1
- MEP Finishes Level 1
- Clark Door Install Level 1
- Polished Concrete Level 1
- Install Passenger and Jump Elevator
- Form and Pour Site Sidewalks
- •Landscaping Along Richmond Street
- •Granite Seawall and Bench Install
Week of September 21, 2026
- Power and Lighting Level 9
- Install Valves and Control Wiring Level 8
- Epoxy Walls and Floors Level 7
- Doors and Frame Level 7
- Casework Install Level 7
- MEP Finishes Level 7
- Ceiling White Out Level 6
- Carpet Level 6
- Lights Level 6
- Rough Clean Level 5
- Base Install Level 5
- Ceiling Install Level 1
- Painting Level 1
- MEP Finishes Level 1
- Clark Door Install Level 1
- Polished Concrete Level 5
- Granite Seawall and Bench Install