Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2- October 4, 2025
- Elbow Street closed for bridge detailing
Construction Updates
Please note, scope may change based on existing conditions found in the field.
September 2025
Week of September 8, 2025
- Deck and detail level 9 and penthouse roof
- Pour level 8
- Continue spray fireproofing level 1 & 6
- Site utility install
- Install MEP risers
- Early wall install level 3 and 4
- MEP install level 3 and 4
- Masonry walls and framing at loading dock
- Install clips at bridge
- Pour bridge slab
- Mobilize curtainwall
Week of September 15, 2025
- Deck and detail penthouse roof
- Pour level 9
- Continue spray fireproofing level 6 and 7
- Site utility install
- Install MEP risers
- Early walls and MEPs on level 4 and 5
- Masonry walls and exterior framing at loading dock
- Shake out and install curtainwall
- Fireproofing at bridge
Week of September 22, 2025
- Deck and detail penthouse roof
- Pour level 9
- Continue spray fireproofing level 7
- Site utility install
- Install MEP risers
- Early walls and MEPs on level 5
- Masonry walls and exterior framing at loading dock
- Curtain wall install
- Install MEPs at bridge