William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - March 27, 2026
  • Elbow Street closed for bridge detailing

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

 March 2026


Week of March 2, 2026

  • MEP install level 10
  • Install roofing level 10
  • Roof flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Build switchgear level 9
  • Install grating at level 9 dunnage
  • Rig and set plumbing equipment level 8
  • Install flashings level 9 and 10
  • Low pressure ductwork and MEP rough level 7
  • Framing level 7
  • MEP overhead and in-wall rough 6
  • Taping and drywall level 5
  • Install metal panel level 4 north
  • Tape level 2
  • MEP rough on level 1
  • Install level 1 curtainwall
  • Core board shafts
  • Frame and Sheath Stair 1
  • Install passenger and service Elevators
  • Install granite level 1 


Week of  March 9, 2026

  • Roof flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Build switchgear level 9
  • Install grating at level 9 dunnage
  • Frame and sheath exterior walls level 9
  • Rig and set plumbing equipment level 8
  • Install flashings level 9 and 10
  • Low pressure ductwork and MEP rough level 7
  • Framing level 7
  • MEP overhead and in-wall rough 6
  • Drywall level 6
  • Drywall, taping, painting level 5
  • Install metal panel level 4 north
  • Prime and paint level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service Elevators
  • Install granite level 1
  • Take down tower crane March 12th to 15th (5am to 7pm)


Week of March 16, 2026

  • Roof flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Install grating at level 9 dunnage
  • Frame and sheath exterior walls level 9
  • Rig and set plumbing equipment level 8
  • Install flashings level 9 and 10
  • In-wall rough and blocking level 7
  • Framing level 7
  • Blocking, drywall and taping level 6
  • Taping and painting level 5
  • Install K-13 level 5
  • Install metal panel mezzanine level
  • Prime and paint level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service elevatorsInstall granite level 1