Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
  • May 26th thru June 30th    Elbow Street for sidewalk installation
  • June 8th thru August 31st  Richmond Street northbound closed for landscaping/sidewalk install
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

June 2026

Week of June 15, 2026

  • Site closed Friday June 19th for Juneteenth
  • Power and lighting Level 9
  • Fire alarm Level 9
  • Install panels and control wiring Level 8
  • Fill and flush equipment Level 8
  • Taping Level 7
  • Sheetrock Level 7
  • Overhead rough/insulation Level 7
  • Install flooring Level 6
  • Bathroom tile Level 6
  • Painting level 6
  • Install flooring Level 5
  • Lab casework Level 5
  • MEP rough on Level 1
  • Drywall Level 1
  • Install passenger and service elevators
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow Streets
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building
     
Week of June 22, 2026
  • Power and lighting Level 9
  • Fire alarm Level 9
  • Install panels and control wiring Level 8
  • Equipment start-up Level 8
  • Fill and flush equipment Level 8
  • Taping Level 7
  • Sheetrock Level 7
  • Overhead rough/insulation Level 7
  • Install flooring Level 6
  • Bathroom tile Level 6
  • Painting Level 6
  • Lab casework Level 5
  • Drywall and taping Level 1
  • Install passenger and service elevators
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow Streets
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building
  • Landscaping along Richmond Street

Week of June 29, 2026

  • Power and lighting Level 9
  • Fire alarm Level 9
  • Install panels and control wiring Level 8
  • Equipment start-up Level 8
  • Taping Level 7
  • Sheetrock Level 7
  • Overhead rough/insulation Level 7
  • Install flooring Level 6
  • Lab casework Level 6
  • Lab casework Level 5
  • Drywall and taping Level 1
  • Service elevator live
  • Install site drainage structures and piping
  • Install light pole bases
  • Form and pour sidewalks on Chestnut and Elbow Streets
  • Cox relocation of conduit
  • Bring landscape to subgrade on west side of building
  • Landscaping along Richmond Street