Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
  • June 8th thru September 6th  Richmond Street northbound closed for landscaping/sidewalk install
 

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

August 2026

Week of August 3, 2026
  • Fire Alarm Level 9
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • Terminate Electrical Panels Level 8
  • Drywall and Tape Hard Ceilings Level 7
  • Epoxy Walls and Floors Level 7
  • Overhead MEP Rough Level 7
  • Lab Casework Install Level 6
  • Install Aluminum Frames Level 6
  • Polished Concrete Level 6
  • Install Aluminum Frames and Glass Partitions Level 5
  • Hoist Infill Level 5
  • Install Sealed Concrete Level 5
  • Fabric Panels Level 5
  • In-Wall Rough Levels 2-4
  • Drywall and Taping Level 1
  • In-Wall Rough Level 1
  • AV Rack Install Level 1
  • Install Passenger and Jump Elevator
  • Install Light Pole Bases
  • Form and Pour Sidewalks on Chestnut and Elbow St
  • Cox Relocation of Conduit Second Shift
  • Landscaping Along Richmond St
     
Week of August 10, 2026
  • Site Closed Monday 8/10 for Victory Day
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • Terminate Electrical Panels Level 8
  • Fill and Flush Hot WAter
  • Epoxy Walls and Floors Level 7
  • Overhead MEP Rough Level 7
  • Lab Casework Install Level 6
  • Install Aluminum Frames Level 6
  • Fabric and Glass Boards Level 6
  • Fabric Panels Level 6
  • Polished Concrete Level 6
  • Install Aluminum Frames Level 5
  • Fabric Panels Level 5
  • Sealed Concrete Level 5
  • In-Wall Rough Levels 2-4
  • Taping Level 1
  • AV Rack Install Level 1
  • K-13 Start Level 1
  • Install Passenger and Jump Elevator
  • Install Light Pole Bases
  • Form and Pour Sidewalks on Chestnut and Elbow St
  • Cox Relocation of Conduit Second Shift
  • Landscaping Along Richmond St

 Week of August 17, 2026
  • Power and Lighting Level 9
  • Install Valves and Control Wiring Level 8
  • Terminate Electrical Panels Level 8
  • Epoxy Walls and Floors Level 7
  • MEP Finishes Level 7
  • Seal Concrete Level 6
  • Fabric Panels Level 6
  • Hub Ceiling Level 5
  • Fabric Panels Level 5
  • Sealed Concrete Level 5
  • Taping Level 1
  • Clark Door Install Level 1
  • K-13 Start Level 1
  • Install Passenger and Jump Elevator
  • Install Light Pole Bases
  • Form and Pour Sidewalks on Chestnut and Elbow St
  • Cox Relocation of Conduit Second Shift
  • Landscaping Along Richmond St