William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - February 27, 2026
  • Elbow Street closed for bridge detailing

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

February 2026


Week of February 2, 2026

  • Snow removal ongoing
  • MEP install level 10
  • Install roofing level 10
  • Run conduit for switchgear from 1 to 9
  • Rig and set plumbing equipment Level 8
  • Curtainwall install 1
  • Install flashings level 9 and 10
  • Low pressure ductwork and MEP rough level 7
  • Framing level 6
  • MEP overhead and in-wall rough level 5 and 6
  • Drywall level 5
  • Drywall and taping level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service elevators
  • Frame stair 1
     

Week of February 9, 2026

  • MEP install level 10
  • Install roofing level 10
  • Roof flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Install grating at level 9 dunnage
  • Rig and set plumbing equipment level 8
  • Curtainwall install 1
  • Install flashings level 9 and 10
  • Low pressure ductwork and MEP rough level 7
  • Framing level 7
  • Framing level 6
  • MEP overhead and in-wall rough 6
  • Drywall level 5
  • Taping level 5
  • Drywall and taping level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service elevators
  • Frame stair 1
     

Week of February 16, 2026

  • Site closed Monday, 2/16, for President’s Day
  • MEP install level 10
  • Install roofing level 10
  • Roof flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Install grating at level 9 dunnage
  • Build exterior walls level 9
  • Rig and set plumbing equipment level 8
  • Curtainwall install 1
  • Install flashings level 9 and 10
  • Low pressure ductwork and MEP rough level 7
  • Framing level 7
  • MEP overhead and in-wall rough 6
  • Drywall level 5
  • Taping level 5
  • Prime and paint level 2
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service elevators
  • Install granite level 1 

     


 


 

aerial view of Danoff construction site 11.2025