William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

 

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
    • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline

November 15, 16, 17 - Tower Crane

  • Street closures on Chestnut Street and Elm Street for tower crane erection, 5:30 AM - 7:00 PM each day (pending approval)
  • Streets will be closed with detours, flagmen, and police details as needed for the protection of the public
  • Rain dates:  November 22, 23, 24 
November 15-17 Road Closure Plan

Construction Updates

Please note, scope may change based on existing conditions found in the field.

November 2024

Week of November 18, 2024

  • Continue earthwork and soil hauling
  • Continue concrete foundations
  • Demobilize assist crane
  • Begin North core form and placement

Week of November 25, 2024

  • Site closed November 28, 2024
  • Continue earthwork and soil hauling
  • Continue North core form andplacement
  • Continue concrete foundations

December 2024

Week of December 2, 2024

  • Continue concrete foundations
  • Continue earthwork and soil hauling
  • Continue North core form and placement

 

 

Sitework map