William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - February 27, 2026
  • Elbow Street closed for bridge detailing

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

February - March 2026


Week of February 23, 2026

  • MEP install level 10
  • Install roofing level 10
  • Roof  flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Install grating at level 9 dunnage
  • Build exterior walls level 9
  • Rig and set plumbing equipment level 8
  • Install flashings level 9 and 10
  • Low pressure ductwork and MEP rough level 7
  • Framing level 7
  • MEP overhead and in-wall rough 6
  • Drywall and taping level 5
  • Prime and paint level 2 
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service elevators
  • Install granite level 1 


Week of March 2, 2026

  • MEP install level 10
  • Install Roofing level 10
  • Roof flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Install grating at level 9 dunnage
  • Rig and set plumbing equipment level 8
  • Install flashings level 9 and 10
  • Low pressure ductwork and MEP rough level 7
  • Framing level 7
  • MEP overhead and in-wall rough 6
  • Prime and paint level 5
  • Prime and paint level 2 
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service elevators
  • Install granite level 1 
  • Tower crane removal March 5-8


Week of March 9, 2026

  • MEP install level 10
  • Roof flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Install grating at level 9 dunnage
  • Rig and set plumbing equipment level 8
  • Install flashings level 9 and 10
  • Low pressure ductwork and MEP rough level 7
  • Framing level 7
  • MEP overhead and in-wall rough 6
  • Drywall and taping level 6
  • MEP rough on level 1
  • Core board shafts
  • Install passenger and service Elevators
     

 

aerial view of Danoff construction site 11.2025