William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline

April 4, 2025 to May 2, 2025

  • Elbow Street closed to pedestrians between Ship Street and Chestnut Street
  • Elbow Street closed to vehicles Monday - Friday 7 AM to 3 PM between Ship Street and Chestnut Street

Image of Danoff Lab site plan
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

May 2025

  • Week of May 5, 2025
    • Continue Structural Steel erection
    • Continue Demo of 70 Ship St
    • Install Waterline off Elbow Street
    • Install Temporary Construction Lights at 1st Floor
  • Week of May 12, 2025
    • Continue Structural Steel erection
    • Continue Demo of 70 Ship St
    • Start Underground Plumbing at Slab on Grade
    • Start Underground Electrical at Slab on Grade
    • Start Mechanical Sleeves and Hangers on Mezzanine Level
  • Week of May 19, 2025
    • Continue Structural Steel Erection
    • Continue Underground Electrical at Slab on Grade
    • Continue Underground Plumbing at Slab on Grade
    • Install rebar and mesh on Mezzanine Level
    • Continue Demo of 70 Ship st.

Danoff Steel Erection graphic