William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction Closure Information & Construction Updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - March 27, 2026
  • Elbow Street closed for bridge detailing
March 12 thru March 20
•Elbow and Chestnut Street closed 6 AM thru 7 PM for tower crane removal

Aerial map of Danoff construction site
 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

 March 2026

Week of March 16, 2026
 

  • Take down tower crane March 17th to 20th (6am to 7pm)
  • Roof flashing level 9 and 10
  • Run conduit for switchgear from 1 to 9
  • Tape and paint walls level 9
  • MEP equipment connections level 8
  • Install final roof level 8
  • Install flashings level 9 and 10
  • In-wall rough level 7
  • Framing level 7
  • MEP overhead rough level 6
  • Blocking and drywall level 6
  • Drywall and taping level 5
  • Install metal panel mezzanine level
  • Prime and paint level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Sheath exterior soffits


Week of March 23, 2026
 

  • Roof flashing level 9 and 10
  • Buildout switchgear level 9
  • MEP equipment connections level 8
  • Install final roof level 8
  • Install flashings level 9 and 10
  • In-wall rough level 7
  • Framing level 7
  • MEP overhead rough level 6
  • Blocking, drywall, taping level 6
  • Tape and paint level 5
  • Install metal panel mezzanine level
  • Prime and paint level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Metal panel exterior soffits
     

Week of March 30
 

  • Buildout switchgear level 9
  • MEP equipment connections level 8
  • Install final roof level 8
  • Install flashings level 9 and 10
  • In-wall rough and blocking level 7
  • Framing level 7
  • Blocking, drywall, taping level 6
  • Tape and paint level 5
  • K-13 install level 5
  • Install metal panel mezzanine level
  • Install ceilings level 2
  • MEP rough on level 1
  • Install passenger and service elevators
  • Install granite level 1
  • Install site drainage structures and piping
  • Install light pole bases
  • Install fencing at electric yard
  • Metal panel exterior soffits