Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
- May 26th thru June 30th Elbow Street for sidewalk installation
- June 8th thru August 31st Richmond Street northbound closed for landscaping/sidewalk install

Construction Updates
Please note, scope may change based on existing conditions found in the field.
June 2026
Week of July 6, 2026
- Power and lighting Level 9
- Fire alarm Level 9
- Install valves and control wiring Level 8
- Taping Level 7
- Hard ceilings Level 7
- Epoxy floors Level 7
- Overhead rough/insulation Level 7
- Install flooring Level 6
- Lab casework install Level 6
- Lab casework Level 5
- Install glass partitions Level 5
- Drywall and taping Level 1
- Install passenger and jump elevator
- Service elevators live
- Install site drainage structures and piping
- Install light pole bases
- Form and pour sidewalks on Chestnut and Elbow Streets
- Cox relocation of conduit
- Landscaping along Richmond Street
Week of July 13, 2026
- Power and lighting Level 9
- Fire alarm Level 9
- Install valves and control wiring Level 8
- Taping Level 7
- Hard ceilings Level 7
- Epoxy floors Level 7
- Overhead rough/insulation Level 7
- Install flooring Level 6
- Lab casework install Level 6
- Lab casework Level 5
- Install glass partitions Level 5
- Polish concrete Level 5
- Install fabric panels Level 5
- Drywall and taping Level 1
- Install passenger and jump elevator
- Install light pole bases
- Form and pour sidewalks on Chestnut and Elbow Streets
- Cox relocation of conduit
- Landscaping along Richmond Streetl
Week of July 20, 2026
- Power and lighting Level 9
- Fire alarm Level 9
- Install valves and control wiring Level 8
- Taping Level 7
- Hard ceilings Level 7
- Epoxy floors Level 7
- Overhead rough/insulation Level 7
- Install flooring Level 6
- Lab casework install Level 6
- Install fabric panels Level 5
- Install glass partitions Level 5
- Polish concrete Level 5
- Install fabric panels Level 5
- Drywall and taping Level 1
- Install passenger and jump elevator
- Form and pour sidewalks on Chestnut and Elbow Streets
- Cox relocation of conduit
- Landscaping along Richmond Street