Facilities and Campus Operations

William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
  • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline
September 2 - November 1, 2025
  • Elbow Street closed for bridge detailing


 

Construction Updates

Please note, scope may change based on existing conditions found in the field.

October 2025

Week of October 6, 2025

  • Continue spray fireproofing level 8
  • Site utility install
  • Install MEP risers
  • Early walls and MEPs on level 5
  • Masonry walls and exterior framing at loading dock
  • Curtain wall install level 2 and 3
  • Install roofing level 5
  • Install roofing at bridge
  • Install parapet walls on levels 8-10
  • Frame level 1 mechanical and electrical rooms
  • Mobilize mast climbers for exterior masonry
     

Week of October 13, 2025

  • Site closed Monday 10/13/25
  • Pour penthouses roof
  • Continue spray fireproofing level 8
  • Site utility install
  • Install MEP risers
  • Early walls and MEPs on levels 5 and 6
  • Masonry walls and exterior framing at loading dock
  • Curtain wall install level 3
  • Install MEPs at bridge
  • Install parapet walls on levels 8-10
  • Install temporary roofing level 8
  • Frame level 1 mechanical and electrical rooms
  • Exterior framing, sheathing, AVB on level 1 


Week of October 20, 2025

  • Spray fireproofing level 9
  • Form and pour penthouse mechanical pads
  • Site utility install
  • Install MEP risers
  • Early walls and MEPs on level 6
  • Masonry walls and exterior framing at loading dock
  • Curtain wall install levels 3 and 4
  • Install MEPs at bridge
  • Install parapet walls on levels 8-10
  • Install temporary roofing level 8
  • Frame Level 1 mechanical and electrical rooms
  • Exterior framing, sheathing, AVB on level 1 
     


 

 

Danoff Steel Erection graphic