Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
Construction Updates
Please note, scope may change based on existing conditions found in the field.
January/February 2025
Week of January 27, 2025
- Continue concrete foundations
- Continue backfill of completed foundations
- Continue waterproofing of foundations
- Continue north core form and placement
- Continue south core form and placement
- Start underground electrical ductbank
- Start underground plumbing
Week of February 3, 2025
- Continue concrete foundations
- Continue backfill of completed foundations
- Continue waterproofing of foundations
- Continue north core form and placement
- Continue south core form and placement
- Continue underground electrical ductbank
- Continue underground plumbing
Week of February 10, 2025
- Continue concrete foundations
- Continue backfill of completed foundations
- Continue waterproofing of foundations
- Continue north core form and placement
- Continue south core form and placement
- Continue underground electrical ductbank
- Continue underground plumbing
- Install drain line along Richmond Street