William A. and Ami Kuan Danoff Life Sciences Laboratories - Construction Information

Construction closure information & construction updates

Construction Closure Overview

June 2024 – February 2027

  • Richmond Street southbound lane closure
  • Richmond Street southbound sidewalk closure
    • Northbound sidewalk remains open
  • Elbow Street northbound sidewalk closure
  • Chestnut Street parking spots to be taken offline
  • Elm Street parking spots to be taken offline

SATURDAY JANUARY 4, 2025

  • Elm Street to be closed from Richmond Street to Chestnut Street

 

November 15-17 Road Closure Plan

Construction Updates

Please note, scope may change based on existing conditions found in the field.

December 2024

Week of December 23, 2024

  • Site closed December 25, 2024
  • Continue concrete foundations
  • Waterproofing of foundations
  • Continue backfill of completed foundations
  • Continue north core form and placement
  • Start south core form and placement of walls
  • Install drain at Richmond Street

Week of December 30, 2024

  • Site closed January 1, 2025
  • Backfill of completed foundations
  • Continue concrete foundations
  • Continue waterproofing of foundations
  • Continue north core form and placement
  • Continue south core form and placement
  • Continue install of drain at Richmond Street
  • Saturday, January 4, 2025:  Elm Street to be closed between Richmond Street and Elm Street for erection of  crawler crane

Week of January 6, 2024

  • Continue concrete foundations
  • Continue backfill of completed foundations
  • Continue waterproofing of foundations
  • Continue north core form and placement
  • Continue south core form and placement

 

 

Sitework map