Construction Closure Overview
June 2024 – February 2027
- Richmond Street southbound lane closure
- Richmond Street southbound sidewalk closure
- Northbound sidewalk remains open
- Elbow Street northbound sidewalk closure
- Chestnut Street parking spots to be taken offline
- Elm Street parking spots to be taken offline
September 2 - November 1, 2025
- Elbow Street closed for bridge detailing
Construction Updates
Please note, scope may change based on existing conditions found in the field.
October 2025
Week of October 6, 2025
- Continue spray fireproofing level 8
- Site utility install
- Install MEP risers
- Early walls and MEPs on level 5
- Masonry walls and exterior framing at loading dock
- Curtain wall install level 2 and 3
- Install roofing level 5
- Install roofing at bridge
- Install parapet walls on levels 8-10
- Frame level 1 mechanical and electrical rooms
- Mobilize mast climbers for exterior masonry
Week of October 13, 2025
- Site closed Monday 10/13/25
- Pour penthouses roof
- Continue spray fireproofing level 8
- Site utility install
- Install MEP risers
- Early walls and MEPs on levels 5 and 6
- Masonry walls and exterior framing at loading dock
- Curtain wall install level 3
- Install MEPs at bridge
- Install parapet walls on levels 8-10
- Install temporary roofing level 8
- Frame level 1 mechanical and electrical rooms
- Exterior framing, sheathing, AVB on level 1
Week of October 20, 2025
- Spray fireproofing level 9
- Form and pour penthouse mechanical pads
- Site utility install
- Install MEP risers
- Early walls and MEPs on level 6
- Masonry walls and exterior framing at loading dock
- Curtain wall install levels 3 and 4
- Install MEPs at bridge
- Install parapet walls on levels 8-10
- Install temporary roofing level 8
- Frame Level 1 mechanical and electrical rooms
- Exterior framing, sheathing, AVB on level 1